Construction of the Fresno River Viaduct in January 2016. The BNSF Railway bridge is visible in the background.

The Fresno River Viaduct is a bridge currently under construction to carry California High-Speed Rail over Route 145, the Fresno River, and Raymond Road in Madera County, California.[1] It is the first permanent structure constructed as part of California High-Speed Rail.[2] The bridge site is located just east of the city limits of Madera, California,[2] approximately 20 miles northwest of the planned Fresno high-speed rail station, and approximately 10 miles southeast of the planned Chowchilla Wye.[3] Because the site is downstream of the John Franchi Diversion Dam, the riverbed is normally dry unless heavy rains cause the dam to overtop.[4][5] The bridge will be 1600 feet long[1] and 25 feet high,[2] and will run parallel to the BNSF Railway bridge over the Fresno River.[6]

Construction began in June 2015 and was expected to take eight to twelve months.[1] Initial work consisted of assembling rebar cages for the bridge columns and pouring concrete.[6] In August, temporary cofferdams were erected to excavate sand to construct the bridge's structural supports.[7] By the end of October, the work on the piles had ended and the rebar skeletons of the 16 columns had been erected.[8] In late March 2016, concrete began to be poured for the bridge's superstructure.[9]

References

  1. 1 2 3 Sheehan, Tim (2015-06-16). "Heavy equipment finally moving on California high-speed rail construction". Fresno Bee. Retrieved 2015-10-30.
  2. 1 2 3 Yurong, Dale (2015-06-16). "We're seeing our first signs of construction for the California High Speed Rail project". ABC30 Fresno. Retrieved 2015-10-30.
  3. "Merced to Fresno Project Section". California High-Speed Rail. Retrieved 2015-10-30.
  4. "Final Environmental Impact Report/Statement, Merced to Fresno: Hydrology and Water Resources" (PDF). California High-Speed Rail Authority. April 2012. pp. 11, 20. Retrieved 2015-11-01.
  5. "Foxglove Shopping Center Draft EIR: Hydrology and Water Quality" (PDF). City of Madera. May 2011. p. 2. Retrieved 2015-11-01.
  6. 1 2 "First Concrete Poured for High-Speed Rail". SCV News. 2015-06-27. Retrieved 2015-10-30.
  7. "High-Speed Rail: Cofferdams Installed in Fresno". SCV News. 2015-08-28. Retrieved 2015-10-30.
  8. Sheehan, Tim (2015-10-30). "High speed rail: Crews prepare next step to building viaduct over Fresno River". Fresno Bee. Retrieved 2015-10-31.
  9. Lurie, George (2016-04-21). "Rail projects begin to alter Valley landscape, impact local businesses". The Business Journal. Retrieved 2016-05-02.

Coordinates: 36°58′59″N 120°01′45″W / 36.983069°N 120.029177°W / 36.983069; -120.029177

This article is issued from Wikipedia - version of the Tuesday, May 03, 2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.