Hydraulic fill

A hydraulic fill is an embankment or other fill in which the materials are deposited in place by a flowing stream of water, with the deposition being selective.[1] Gravity, coupled with velocity control, is used to effect the selected deposition of the material.

Borrow pits containing suitable material are accessible at an elevation such that the earth can be sluiced to the fill after being washed from the bank by high-pressure nozzles. Hydraulic fill is likely to be the most economic method of construction. Even when the source material lacks sufficient elevation, it can be elevated to the sluice by a dredge pump. In the construction of a hydraulic fill dam, the edges of the dam are defined by low embankments or dykes which are built upward as the fill progresses. The sluices are carried parallel to, and just inside of, these dykes. The sluices discharge their water-earth mixture at intervals, the water fanning out and flowing towards the central pool which is maintained at the desired level by discharge control. While flowing from the sluices, coarse material is deposited first and then finer material is deposited (fine material has a slower terminal velocity thus takes longer to settle, see Stoke's Law) as the flow velocity is reduced towards the center of the dam. This fine material forms an impervious core to the dam. The water flow must be well controlled at all times, otherwise the central section may be bridged by tongues of coarse material which would facilitate seepage through the dam later.

Hydraulic fill dams can be dangerous in areas of seismic activity due to the high susceptibility of the uncompacted, cohesion-less soils in them to earthquake liquefaction. In these situations, a dam built of compacted soil may be a better choice. The Lower San Fernando Dam [2] is an example of a hydraulic fill dam that failed during an earthquake.

The Fort Peck Dam is an example of a hydraulic fill dam that failed during construction where the hydraulic filling process may have contributed to the failure.[3]

Hydraulic fill is also a term used in hard rock mining and describes the placement of finely ground mining wastes into underground stopes in a slurry by boreholes and pipes to stabilize the voids.

References

  1. "Initiating Hydraulic Fill Projects" (PDF). International Association of Dredging Companies. Retrieved 16 December 2013.
  2. "The Lower San Fernando Dam" (PDF). Retrieved 16 December 2013.
  3. French, Brett. "Fort Peck Dam damage from 2011 being repaired". The Bismarck Tribune. Retrieved 16 December 2013.
This article is issued from Wikipedia - version of the Thursday, January 16, 2014. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.