Kaheawa Wind Power

Kaheawa Wind Power

Phase I
Location of Kaheawa Wind Power in Hawaii
Country United States
Location Maui, Hawaii
Coordinates 20°48′49″N 156°33′4″W / 20.81361°N 156.55111°W / 20.81361; -156.55111Coordinates: 20°48′49″N 156°33′4″W / 20.81361°N 156.55111°W / 20.81361; -156.55111
Status Operational (I)
Operational (II)
Construction began October 28, 2005 (I)
2011 (II)
Commission date June 8, 2006 (I)[1]
July 2, 2012 (II)
Construction cost $69 million (I)
$67 million (II)
Owner(s) First Wind
Wind farm
Type Onshore
Avg. site elevation 2,650 ft (808 m)
Site usage Pasture
Site area 200 acres (81 ha) (I)
143 acres (58 ha) (II)
Hub height 51.2 m (168 ft)
Rotor diameter 70.5 m (231 ft)
Rated wind speed 12 m/s (39.4 ft/s)
Power generation
Units operational 34
Make and model GE Energy: GE 1.5se
Nameplate capacity 51 MW
Capacity factor 43%
Annual generation 126 TWh
Website
www.kaheawa.com
Phase I & II, all 34 Wind turbines

Kaheawa Wind Power is one of the largest wind farms in Hawaii. It is located on the island of Maui above the town of Maalaea in the West Maui Mountains. Phase one (KWP I) of the project was completed in 2006 by developer and operator First Wind and produces 30 MW from 20 GE Energy 1.5 MW wind turbines.[2]

Phase two (KWP II), completed in July 2012, built 14 turbines below phase one with an additional 21 MW for a total capacity of 51 MW serving 18,700 homes.[3] Kaheawa is the first wind farm in the United States to use a Habitat Conservation Plan (HCP) to protect the long term health of local species, including three endemic birds and one endemic bat.[4]

Kaheawa is helping to contribute to the goals of the Hawaii Clean Energy Initiative, a memorandum of understanding between the State of Hawaii and the U.S. Department of Energy to reduce imported oil and supply 70 percent or more of Hawaii's energy from clean and renewable energy by 2030.

Geography

Kaheawa Wind Power is located between the 2000–3000 foot elevation in Kaheawa Pastures in the Lahaina District, on the slopes of the Ukumehame land division (ahupuaʻa) of the West Maui Mountains.[5] The site is bounded by Papalaua Gulch in the west and Manawainui Gulch in the east.

Phase two of the project is located on the Kaheawa Ridge at the 1800–2700 foot elevation, just southeast of KWP I.

Background

The first wind project was proposed in 1996. Zond Pacific installed a series of six anemometers in the area to collect and study wind data. The project was developed by several companies before UPC Wind Partners, LLC and Makani Nui Associates, LLC formed a partnership. An environmental impact statement (EIS) was approved in 1999, followed by a Conservation District Use Application in 2003.[6]

Development

In September 2006, Kaheawa Wind Power began negotiating with the state Board of Land and Natural Resources to expand the wind farm.[7] In February 2011, MECO finalized a power purchasing agreement to buy power from an additional 14 turbines under construction for phase two of the wind farm, which planned to add a new 10 MW battery energy storage system (BESS).[8] The 14 new turbines and battery storage system went online on July 2, 2012.[9]

Specifications

Specifications
Manufacturer GE Energy
Model GE 1.5se
Tower height 51.2 metres (168 ft)
Blade length 35 metres (115 ft)
Total maximum height 90 metres (295 ft)
Turbine weight 100 tonnes (98 long tons; 110 short tons)
Maximum turbine effect 1.5 megawatts (2,000 hp)
Total nameplate capacity (maximum output) 51 megawatts (68,000 hp)
Electricity generated per annum 126,000 GW·h (450,000 TJ)
Capacity factor 43%
Total carbon dioxide (CO
2
) displaced per annum
77,000 tonnes (76,000 long tons; 85,000 short tons)
Total sulphur dioxide (SO
2
) displaced per annum
590 tonnes (580 long tons; 650 short tons)
Total nitrogen oxides (NO
x
) displaced per annum
160 tonnes (160 long tons; 180 short tons)

Habitat

Kaheawa Wind Farm looking north

The environmental impact statement for Kaheawa led to the development of a habitat conservation plan (HCP), the first HCP ever used for a wind farm of this scale in the United States. The plan helps fund conservation efforts for four protected species, including three endemic birds and one endemic bat: the Hawaiian goose (nene), the Hawaiian petrel (ʻuaʻu), the Hawaiian shearwater (ʻaʻo), and the Hawaiian hoary bat (ʻopeʻapeʻa).[10] The project is also researching how to best protect the nesting areas of seabirds.

The initial construction of the wind farm required restoration efforts for several plant species in the area. More than 24,000 native plants were eventually restored, comprising species such as Dodonaea viscosa (aʻaliʻi), Metrosideros polymorpha (ʻŌhiʻa lehua), Bidens micrantha, (koʻokoʻolau), Wikstroemia oahuensis (ʻakia), and Heteropogon contortus (pili).[11]

The habitat also includes Sida fallax Sosa (ʻilima), Sophora chrysophylla (māmane), Lycopodiella cernua (wāwaeʻiole), and two invasive species, Leucaena leucocephala (koa haole Sosa) and Cenchrus ciliaris.[12]

See also

Notes

  1. Pacific Business News 2006
  2. "Maui Island: Kaheawa Wind Farm". Existing Wind Farms. HECO. Retrieved November 25, 2012.
  3. Shimogawa 2011; Hao 2006, p. C1; Hawaiian Electric Company 2011; Osher 2012; Imada 2012.
  4. Eagar 2008; Kaheawa Wind Power 2006, p. 6
  5. Kaheawa Pastures Wind Energy Generation Facility Habitat Conservation Plan 2006, p. 1
  6. Kaheawa Wind Power, LLC 2005; Kaheawa Wind Power, LLC 2006
  7. Leone 2006
  8. MECO gets ok to buy power from Kaheawa II wind farm 2006
  9. Imada 2012.
  10. The Maui News 2010; Kaheawa Wind Power, p. 6
  11. Wireless News 2011
  12. Starr, Plants of Hawaii; Kaheawa Wind Power 2006, p. 14, 16

References

Further reading

External links

Wikimedia Commons has media related to Kaheawa Wind Power.
This article is issued from Wikipedia - version of the Sunday, April 17, 2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.