La Pepa Bridge

Constitution of 1812 Bridge

View of the bridge, in August 2015.
Coordinates 36°31′29″N 6°15′25″W / 36.52472°N 6.25694°W / 36.52472; -6.25694Coordinates: 36°31′29″N 6°15′25″W / 36.52472°N 6.25694°W / 36.52472; -6.25694
Carries 6 lanes, (2 lanes each way & 2 tram way)
Crosses Bay of Cadiz
Locale Cadiz,  Spain
Official name Constitution of 1812 Bridge
Characteristics
Design Cable-stayed bridge by Javier Manterola
Total length 3,092 meters (10,144 ft)[1]
Width 34.3 meters (113 ft)
Longest span 540 meters (1,770 ft)[1]
History
Opened 24 September 2015
Statistics
Daily traffic expected 20,000 AADT

The Constitution of 1812 Bridge, also known like La Pepa Bridge (El puente de la Constitución de 1812 or Puente de La Pepa in Spanish), is a new bridge across the Bay of Cadiz, linking Cadiz with Puerto Real in mainland Spain.

Cadiz's first bridge, the Carranza bridge, was inaugurated in 1969, and is now crossed by some 40,000 vehicles per day. In 1982 the Spanish government accepted the need for a second bridge.

It will have two 180 m pylons, one in the sea and the other in Cabezuelas Harbour, a 540 meters span and a 69 meters of vertical clearance. The bridge also includes a 150 meters removal span. The bridge is actually in service.

It is the second bridge that crosses over to Cádiz from the mainland, after Carranza bridge, and one of the highest bridges in Europe, with gauge of 69 meters and 5 kilometers in total length. It will be a suspension bridge with large towers: 187 meters of the sea and 181 meters of earth. Its the third access to the city, along with the isthmus San Fernando and the Carranza bridge. Given the large width of the board, it will be high capacity bridge: motorway with two lanes in each direction and two lanes reserved for metropolitan public transport such as the new tram system.

The bill was drafted by the engineer of roads, canals and ports Javier Manterola. The works were scheduled for completion in 2012, coinciding with the bicentenary of the Spanish Constitution of 1812, which was written in Cádiz. However, due to cuts in public works required by the current economic crisis, the work is more than three years late.

In summer 2013 the work had progressed but at a slower pace. Later, since early 2014 the work progressed at a good pace, highlighting the installation of its cable-stayed span and hiring more staff working every day (including night shifts). As of the first half of 2015, the bridge structure is completed, providing full completion in September of the same year.[2]

As data highlights:

The bridge connects the neighborhood of San Pedro River to Puerto Real with neighborhood of La Paz of Cadiz.

The construction project

View from the Port of Cadiz.
La Pepa Bridge is an extension of CA-35 road to cross the Cadiz Bay. Carranza Bridge is an extension of CA-36 road. They save 20Km (12.75 mi).

The proposed construction of a new access to the city of Cadiz by a bridge over the Bay and has its starting point in the Order of Highways Studies during April 2003, which in turn took account of various studies from 1989. This projects aims was to respond to traffic congestion problems that have been suffering from the access to Cadiz from Puerto Real (Bridge José León de Carranza and CA-33).

In the draft were studies for three riders that links the N-443 in the San Pedro Bay crossing access into Cádiz:

In all three cases a cross section separated by two lanes, shoulders and median lanes are envisioned.

Regarding the crossing structure Bay, the three paths are designed in submerged tunnel. Moreover, in the "A" alternative solution fixed bridge large gauge was studied because it was the only one whose configuration permitted naturally, across a single alignment channel surfing and having a path straight admitting great light openings for the passage of ships. Similarly, three alternatives were studied bridge: archery, cable-stayed and suspension.

The "A" alternative structure bridge for crossing the Bay was selected as the best solution for urban traffic on both banks of the Bay, the lowest investment also considered that nicely integrates both urban planning and landscape.

Of the different types of bridge studied, the braced was selected as the lowest cost and the simplest structural concept.

Execution of the work

Its construction has been contracted to the Joint Venture (UTE) formed by Dragados and DRACE (Special and Dragados Construcciones). The project has a budget of 273 millon euros, and their duration is estimated at 42 months.

Workers are 500 direct employment in times of maximum intensity.

Description

Longitudinal view of the bridge
Longitudinal view at night.

It is a highway whose speed adopted in the project, as permitted approval of the draft, has been set at 80 km/h, justified based on the urban nature of the performance.

The bridge has a total length of 4580 meters, with the following lights in the sea:

The suspension bridge is the highest stretch with maximum longitudinal slope of 5%. On land the bridge is built on the industrial area of La Cabezuela, releasing the existing road condition.

It has three lanes in each direction for vehicular traffic, with central median 0.8 meters with a rigid barrier, and side sidewalks with net width of 1.30 meters. The total width of the bridge is 30.5 meters except where the bracing section expands 32.5 meters to accommodate suspension struts.

Dredging

The layer of Quaternary materials is dredged so that sidewalks foundation of pile caps settle to the firm layer of Pliocene, and poured into the high seas.

Bridge pylons

Of the 39 support, 37 batteries + 2 stirrups, 12 are in the sea, all by "'in site' 'piles 2 meters in diameter, with embedding in the Pliocene.

Stirrup Cádiz

The bridge begins in a vial, with the preferred direction to and from the new bridge, a roundabout in the capital, maintaining connections and access to it on the surface.

Cadiz Access

Its length is 581.2 meters with a mixed structure and topped with concrete ribbed floor slabs. The vain guy is 75 meters above the batteries, which are supported by pylons. The pylons are 30 meters deep with 4-6 pylons.

Battery sections are formed by a double gap with widths ranging from 4.00 to 2.9 trapezius meters depending on the height and between 32.079 meters and 7,804 meters. At the top of this stack, it widens a reach of 10.5 meters which is to gather support with neoprene Teflon, 2700 tons payload, except for the battery 1 will be 2500 tons.

Night view of the center of the bridge (december 2015).