Levis De-Icer
The Levis De-Icer is a High voltage direct current (HVDC) system, aimed at de-icing multiple AC power lines in Quebec, Canada. It is the only HVDC system not used for power transmission.
In the winter of 1998, Québec's power lines were toppled by icing, sometimes up to 75 mm. To prevent such a damage, a de-icing system was developed.[1]
The Levis De-Icer can use a maximum power of 250 MW; its operation voltage is ±17.4 kV. It can be used on multiple 735 kV AC power lines.
When there is no icing, the Lévis De-Icer installed at Hydro-Québec's Lévis substation Coordinates: 46°42′17″N 71°11′39″W / 46.70472°N 71.19417°W operates as static VAR compensator improving the stability of the AC lines.
What the De-icer is and what it does
Because of what happened in Quebec in the winter of 1998, Hydro-Quebec TransEnergie created a De-icing machine to insure that another event like this wouldn't happen again. The De-icer is a machine that runs a high direct current (DC) into a selected transmission line in order to melt the ice on it. However, because the operation in this mode may be very infrequent, when the installation is not being used as a De-icer it is used as a Static Var Compensator, SVC for short, by using the HVDC valves as a Thyristor Controlled Reactor.[2] An innovative design is used, minimizing the power losses of the valves in SVC mode. The reason an AC current wasn't used is because AC current requires a lot of reactive support. It would take a much higher amount of voltage to push the necessary current through the line.The high voltage system in Quebec runs in two transmission corridors, one high voltage system runs in the north-west from the main load centres of Montreal and Quebec and the other runs north-east along the Saint-Lawrence river. It is the latter corridor that is mainly in an area prone to ice storms that deposit ice on the transmission lines.
How it works
The required power line is configured in de-icing mode after being separated from their AC circuit. Then, a line de-icing circuit is created by a set of disconnect switches controlled by the DCU which sends all of the commands to the de-icing converter. The DC current is slowly raised to reach the desired level of current. The de-icing disconnect switches are opened, and the DCU then releases the power line back to the AC network.[3] The lines to be de-iced must stay in normal operation during the entire period of DCU development and start-up. The final installation of the SVC/ de-icer requires a de-icing line equipment pre-operational testing before being installed.The lines being de-iced must stay in normal operation during the start-up as well as throughout the whole period of DCU development. This system is rarely used, only for critical conditions as the operators would be under heavy stress and the man-machine interface (MMI) must be on guided mode. For the five lines being de-iced, there are 13 line topologies that have between 40 to 90 actions per line to be performed during the de-icing process. Out of the five lines, four have three de-icing circuit topologies and the other one only has one. The DCU must offer the possibility to manually confirm the equipment’s state to the operator in order to continue the process as there is always a chance of communication failure. Flexible stimulation sequences used for control logic and MMI validation, pre-operational testing and operator training are required for line equipment and SVC. For 735 kV lines, de-icing takes place in three steps while 315 kV double circuit lines only need one. A DCU supervises and coordinates all the actions required for de-icing each line in order to provide network security and ensure the de-icing sequences are reliable.
De-Icing Currents
The current of the conductor needs to be just high enough to melt the ice on it without actually going above the thermal limit of the conductor. An ordinary 735 kV line with a bundle of four 1354 MCM conductors per phase, requires a de-icing current of 7200 A per phase.[4] At -10 degrees Celsius and wind velocity at 10 km/h, it would take 30 minutes of current injection on a phase to melt 12mm of radial build-up of ice.[4]
Description of the de-icing concept at Levis
The dc converter at Lévis will be used to de-ice 5 lines: four 735 kV single-circuit lines and one 315 kV double-circuit line.[4] Because of the different lengths and sizes of the conductor, the dc installation needs to be able to operate in various voltages and currents. To be de-iced, the line must be closed off from the ac current at both ends. Line conductors are used to form a closed loop.
Modes
In the de-icer mode
According to Chris Horwill (AREVA T&D) there are four main design ratings in the de-icer mode.[1] The first one is the Standard de-icer mode. It works at 250MW and 7200A from ±17.4kV at 10 °C. The second one is the Verification mode. It works at 200MW and 5760A from ±17.4kV at 30 °C.The third one is the 1-hour overload. This one works at 300MW and 7200A from ±20.8kV at 10 °C. The last one is the Low ambient overload. It works at 275MW and 7920A from ±17.4kV at -5 °C. KV is the voltage and A is the currents. The range of operation of the current and voltage is large because all of the sections have different characteristics.
Circuit Schematic
In "de-icer" mode, the installation provides a controlled high current of dc (direct current) power source which feeds a resistive load. The normal current rating in the de-icer mode is 7200 Adc, defines at an ambient temperature of +10 °C. The current rating is too high for a single converter bridge based on present-day HVDC technology. However, with two converter bridges in parallel, the required dc current per bridge can be met with 125mm thyristors used in HVDC converters. With two thyristor converters connected in parallel, there are several possible circuit topologies. The 3 main alternatives considered were: Twelve Pulse Circuit, Double Twelve Pulse Circuit, Double Six Pulse Circuit.[4]
Twelve Pulse Circuit
In this circuit, the two bridges are fed from separate windings of the step down transformer. To improve harmonic cancellation, they have a 30° phase shift between them. Since the two bridges are connected in parallel, a specialised “Inter-Phase Transformer” is required to balance the differences in their emf. Also, this system requires a complex, multi-winding, step-down transformer.
Double Twelve Pulse Circuit
In this circuit, two whole, 12 pulse bridges that are series-connected, are connected in parallel. For this one, the “Inter-Phase Transformer” is eliminated because the emf produced by the bridges is the same. The step-down transformer, like in the twelve pulse circuit, is also complex, along with the thrystor valves and their interconnecting busbars.
Double Six Pulse Circuit
This is a simple connection between two six-pulse thyristor bridges. The de-icer function can be achieved with only a two-winding step-down transformer. Unlike the other two, this circuit can simple controller because the two thyristor bridges can be triggered directly in parallel. As a result, this circuit produces a broader range of harmonic currents and voltages.
In the SVC mode
According to Chris Horwill, there are also four main design ratings in the SVC mode.[1] The first one is the Dynamic range. This one is at 225 Mvar, or -115 Mvar at nominal voltage. The next one is the Target voltage. It is at 315kV±5%. The third one is just the Slope. And the last one is 3% on Mvar.
See also
References
- 1 2 3 "The Hydro Québec De-icer Project at Lévis substation" (PDF). Retrieved 2010-04-26.
- ↑ Horwill, C; Davidson, C C; Granger, M; Dery, A. "thaw point". IEEE Xplore. Power Engineer. Retrieved 2014-11-17.
- ↑ Davis, Kathleen. "A Short Overview of Hydro-Québec’s De-icing System Control Unit". Electric Light & Power. Penn Well Publishing Co. Retrieved 2014-11-17.
- 1 2 3 4 Horwill, C; Davidson, C C; Granger, M; Dery, A. "An Application of HVDC to the de-icing of Transmission Lines". IEEE Xplore. AREVA T&D Power Electron. Activities, Stafford. Retrieved 2014-11-17.