Nextgen Networks

Nextgen Group Pty Ltd
Private
Industry Telecommunications
Founded 2001
Headquarters Melbourne
Owner Ontario Teachers' Pension Plan
Leighton Holdings
Website http://www.nextgengroup.com.au/
NextGen Networks pit

Nextgen Networks is an Australian communications company which is owned by Ontario Teachers' Pension Plan (70%) and Leighton Holdings (30%), one of Australia's major companies.

Nextgen's Network is based on a geographically protected national network, with the Brisbane to Melbourne link utilising self-healing SDH two-fibre ring architecture. The Ring System covers Brisbane, Sydney, Canberra and Melbourne and a Flat Ring Link through to Adelaide and Perth as well as covering 70 major and regional population centres along the route. The Network covers a total of 8,500 km.

History

The Network was constructed in 2002 and cost around $850 million to construct as a Joint Venture of Leighton Contractors ($140m) and Macquarie Bank using state of the art equipment from suppliers such as Lucent and financed by a consortium including Leighton Holdings, Macquarie Bank, National Australia Bank, Deutsche Bank, UBS Capital and WestLB.

Visionstream (another subsidiary of Leightons) constructed the Network consisting of four network loops each with 12 fibre pairs, with each fibre pair capable of 800Gbit/s. The network owners intention was to provide the highest network quality, which led to the use of using many state of the art technologies (at the time).

Lucent supplied the TrueWave RS G655 Fibre developed by Bell Labs to provide high bandwidth capacity and specially designed for long distance DWDM optical cables. Being a Non-zero dispersion shifted fibre it has minimum light dispersion, allowing signals to travel long distances with enough dispersion to prevent crosstalk from adjacent signals. It was built to Australian conditions to prevent against not only rodents but wombats, christmas tree roots and erosion from black soil.[1]

Lucent also supplied newest technology WaveStar OLS 400G DWDM systems and WaveStar Bandwidth Manager.

Nettest's QUESTfiber technology supplied the remote fibre test system (the largest network of its type in the Australia Pacific region) within the Nextgen Networks DWDM network. This gives the benefit of a fully managed network backbone with minimal downtime, when a fault is detected the location is known to within a few metres, as well as showing the health of the cables and its segments, allowing for preemptive maintenance where cable is showing signs of distress.[2]

The building of the network

Visionstream commenced building of the Network on 15 June 2001 with the first soil being turned and commencement of laying the fibre 40 km west of Young, New South Wales at Milvale, after many months of project management planning which included sourcing of materials, negotiating access along the route that the cable and equipment will travel, environmental management and working with indigenous leaders to fully gps map sensitive areas to avoid damage.

The project was brought in ahead of schedule in May 2003, construction was handed over from Visionstream to Nextgen Networks in four main Stages occurring at the following dates.

Stage Location Handover Date
Stage 1 Melbourne - Sydney Loop 30 September 2002
Stage 2 Sydney - Brisbane Loop 20 January 2003
Stage 3 Melbourne - Adelaide 7 December 2002
Stage 4 Adelaide - Perth 15 May 2003

Activities included route construction, urban works, cultural heritage walkouts and the construction of Primary Nodes in each capital city on the route (the Primary Nodes serve as the prime point of interconnection in the network by which customers will access their services).[3]

During 2002 trouble hit the consortium of Nextgen Networks, and although the network was solid the traffic and sales needed to support the financing unfortunately did not eventuate, During the twelve month price war competition bit hard on Nextgen and the other intercity cable providers with the price of backhaul between Australian cities dropping by 70% leaving Nextgen without the funds it needed to repay the debt. This situation was repeated right around the world with many similar owners of fibre optic cables also in financial difficulty and here in Australia with another major Fibre Optic Cable player Amcom backed IP1 Australia who built cable networks from Melbourne through to Perth going into receivership and bought at a fire sale price of $45m (about a quarter of its construction cost of $160m ) by Telstra. Also during this period, a multi terabit international cable Nava-1 was shelved.

On 23 June 2003 administrators were called in by the National Australia Bank.[4]

Assured of significant financial commitment by AARNet to utilize the network,[5] on 24 December 2003 Leighton Holdings acquired Nextgen Networks[6] for a total between $20m and $30m with the banking syndicate having a share in the company's growth for the next 10 years. Nextgen became a full subsidiary of Leighton Holdings and is therefore now debt free.