River Foss Barrier
The River Foss Barrier is a floodgate that straddles the River Foss in York, England at the confluence of the Rivers Ouse and Foss just south of Clifford's Tower. The barrier was opened in 1988 after flooding from the Foss and two other becks caused more damage to properties in the city than when the Ouse was in spate. The purpose of the barrier is to prevent backing up of floodwater from the Foss when it meets the surgewater of the Ouse and cannot drain away.[1] The pumps adjacent to the barrier move water from the Foss into the Ouse.[2]
History
After many years after flash flooding, the York Water Authority commissioned the River Foss Barrier. Work on the barrier commenced in October 1986 and the barrier was opened in November 1988.[3] The main aim of the defence is to prevent back wash from the River Ouse into the River Foss causing flooding upstream of the River Foss.[4]
A probability analysis was carried out for flows in the River Foss combined with high levels in the River Ouse. This indicated a maximum flow of 30 tonnes (30 long tons; 33 short tons) of water per second. In March 2016, a budget was approved to increase capacity to 40 tonnes (39 long tons; 44 short tons) per second.[5]
The barrier weighs 16.5 tonnes (16.2 long tons; 18.2 short tons) and is operated as a turnover lift gate. When in closed state, it is held horizontally above the river and boats and barges pass underneath whilst regular and efficient maintenance can be performed.[6]
The normal water level at York is established as 5 metres (16 ft) Above Ordinance Datum (AOD)[7] and the duty officer is alerted when the River Ouse reaches 7.4 metres (24 ft) AOD. After 7.8 metres (26 ft) AOD is reached, the barrier is lowered into the Foss. Boats are alerted by way of visible and audible alarms and after the alarm is sounded, the pumps are activated, the silt from bed is cleared and the barrier can drop into a tight fit.[6]
The electrically driven barrier takes 4 minutes to lower into position. Eight pumps transfer 30 tonnes (30 long tons; 33 short tons) of water per second from River Foss into River Ouse through the side culvert. These pumps maintain the water level of the Foss at around 6.5 metres (21 ft) AOD. When the flood subsides and the level of the Ouse drops to 6.5 metres (21 ft), the levels of before and after barrier are equalised.
Warning alarms sound to alert everyone before the gate is opened and the pumps shut down.
Site information
|
For current levels click link below
http://www.gaugemap.co.uk/#!Map/Summary/2059/2174 links to Shoothill GaugeMap |
possible flooding around foss river barrier |
---|
Side view
|
Top view |
---|---|
With barrier up |
With barrier down |
Flooding (26 december 2015, Boxing day flooding)[8]
On 26 December 2015, too much water entered the River Foss causing a possible overspill and damage to the electrical services of the barrier. A telephone conference with senior county bodies was convened and it was decided to open the barrier to prevent overflooding. At this time, the level was 20 centimetres (7.9 in) below the flood level (10.2 metres (33 ft)) on 4 November 2000.
It was decided that it would be better to have barrier open, rather than stuck shut by the waterlogging of the electrical services.[2] This decision resulted in a few hundred houses in York city centre being flooded but spared another few hundred houses upstream.
Improvements[9]
In March 2016, extra funds were allocated to upgrade the pumps to 40 tonnes of water per second (from 30 tonnes per second) and moving the electrics to safer point.[10]
Extra modern software to monitor river levels was also bought.
Reports have been published that reveal new pumps are to be installed by September 2016.[10]
100 staff and contractors will work 20 months to complete the upgrade to the barrier.
The existing barrier will continue to operate until all improvements have been completed.
Flood defence scheme
The River Foss Barrier is part of a wider scheme that includes weirs, dams, temporary storage schemes, walls, barriers and temporary water wall that all contribute to reducing, diverting, holding back and preventing domestic overspill in the event of an extraordinary weather event.
References
- ↑ "Reducing the risk of flooding" (pdf). Environment Agency. February 2009. p. 10. Retrieved 22 March 2016.
- 1 2 "The Foss Barrier: reducing the risk of flooding". Gov.uk. 26 January 2016. Retrieved 22 March 2016.
- ↑ Dooks, Brian (28 December 2005). "Flood barrier to be checked on-line". Yorkshire Post. Retrieved 22 March 2016.
- ↑ "River Foss Flood Alleviation Scheme" (pdf). Environment Agency (NRA). Information Services Unit. p. 7. Retrieved 22 March 2016.
- ↑ Laycock, Mike (11 March 2016). "Foss Barrier upgrade: all eight pumps will be replaced - new pumps taking 40 tonnes per second". York Press. Retrieved 22 March 2016.
- 1 2 "Reducing the risk of flooding" (pdf). Environment Agency. February 2009. p. 12. Retrieved 22 March 2016.
- ↑ "reducing the risk of flooding" (pdf). Environment Agency. February 2009. p. 4. Retrieved 22 March 2016.
- ↑ "BBC - funding for Foss barrier". BBC News. Retrieved 15 March 2015.
- ↑ "£13m flood prevention scheme launched in devastated city". The Northern Echo. Retrieved 21 March 2016.
- 1 2 "New pumps confirmed for York's Foss flood barrier". BBC News. Retrieved 21 March 2016.
External links
Coordinates: 53°57′08.4″N 1°04′42.3″W / 53.952333°N 1.078417°W