Seyrantepe Dam

Seyrantepe Dam

Aerial photo of the dam and its power station
Location of Seyrantepe Dam in Turkey
Country Turkey
Location Karakoçan on the border of Elazığ and Tunceli Province
Coordinates 39°1′15.68″N 39°53′29.87″E / 39.0210222°N 39.8916306°E / 39.0210222; 39.8916306Coordinates: 39°1′15.68″N 39°53′29.87″E / 39.0210222°N 39.8916306°E / 39.0210222; 39.8916306
Purpose Power, regulation
Status Operational
Construction began 2003
Opening date 2008 (2008)
Dam and spillways
Type of dam Embankment, sand and gravel-fill
Impounds Peri River
Height (foundation) 48.5 m (159 ft)
Height (thalweg) 36 m (118 ft)
Power station
Operator(s) Limak Energy and Bilgin Energy
Commission date September 2008
Type Conventional
Hydraulic head 36 m (118 ft) (gross)
Turbines 2 x 29.39 MW Francis-type
Installed capacity 58.78 MW
Annual generation 180 GWh

The Seyrantepe Dam is an earth-fill embankment dam on the Peri River (a tributary of the Euphrates), located 15 km (9 mi) northwest of Karakoçan on the border of Elazığ and Tunceli Provinces, Turkey. Its primary purpose is hydroelectric power generation and is the fifth dam in the Peri River cascade. Construction on the dam began in 2003 and its power station was commissioned in 2008. It contains two 29.39 MW Francis turbine-generators for a total installed capacity of 58.78 MW.[1] It is owned and operated by Limak Energy and Bilgin Energy.[2] The sand and gravel-fill dam is 48.5 m (159 ft) tall.[3]

See also

References

  1. "Seyrantepe Dam and Hydroelectric Power Plant" (in Turkish). Bilgin Energy Investment Holding Co. Retrieved 23 June 2015.
  2. "Seyrantepe Dam and HEPP". Enerji Atlasi. Retrieved 23 June 2015.
  3. "List of facilities dam and hydropower" (PDF) (in Turkish). Suyapi. Retrieved 23 June 2015.
This article is issued from Wikipedia - version of the Saturday, March 05, 2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.