TPP Kostolac B3

TPP Kostolac B3 is a plan to build a third unit of the Kostolac B coal fired thermal power plant which installed capacity of 350 MW. For the purposes of running the new plant, expansion of an open pit mine Drmno from 9 to 12 tons of coal annually is planned.[1][2] There are already existing units Kostolac A1, A2, B1 and B2 and Drmno and Cirikovac open cast mines at the site.

On 20 November 2013, Elektroprivreda Srbije, Tеrmoеlеktranе i kopovi Kostolac and Chinese corporation CMEC signed an agreement on construction. Authorities announced that the construction of the power plant is expected to begin by the end of 2014 and to be finished by 2019. Together with the existing blocks B1 and B2 the new plan will satisfy about 20% of Serbia's electricity needs. Zhang Chun, president and CEO of CMEC said that the new thermal power plant will have a positive impact on the environment, because it will comply with the emissions requirements of the European Union scheduled for 2018.[1]

Ownership

Company Tеrmoеlеktranе i kopovi Kostolac is a subsidiary of Elektroprivreda Srbije which is 100% owned by the state of Serbia.[3]

Financing

The project depends on financing from the China Exim Bank and unnamed commercial banks, and on a state guarantee from the Government of Serbia for these loans. The 2014 Serbian state budget allocates two guarantees for the project – US$107 million for unnamed commercial banks and US$608 million for the China Exim Bank.[4] Total value of the project amounts to US$715.6 million.[1]

Controversial issues

Inadequate environmental impact assessment

NGOs are of the opinion that the Environmental impact assessment for the TPP Kostolac B3 is inadequate since it excludes the expansion of the Drmno open-cast mine, does not mention expected levels of emissions to air from heavy metals and does not consider alternative locations or alternative technologies. There is also no mentioning of transboundary impacts even though the site is just around 15 km from the Romanian border and even nearer to the River Danube. NGOs also stress that data sources cited in the study for environmental and health information are outdated (from 2006) and very limited.[5]

On June the 2nd 2014 Serbian NGO CEKOR (Centre for Ecology and Sustainable Development) submitted a formal complaint in front of the Serbian national administrative court against the government’s decision to approve the Environmental Impact Assessment study for the construction of a new unit at the TPP Kostolac B. The complaint, in which the CEKOR exposes failings in the EIA process, is the first of its kind to reach Serbian courts.[5]

Absence of the public procurement procedure

The signing of a contract with CMEC on 20 November 2013 was done without public tender.[1] This is justified by the Serbian government on the basis of Public procurement act, article 2, which says that projects signed under inter-state agreements with other states do not need tender processes.[6] Given the fact that Serbia has the obligation of aligning itself with the EU legislation, the question arises if the law is in accordance with the EU public procurement and state aid legislation.[7]

Events

2014 Floods

Floods in May 2014 threatened to reach Kostolac B thermo power plant, however plant workers, fire-fighters and civilian volunteers managed to contain the water by building embankments.[8][9] Given the fact that during floods RB Kolubara suffered huge damages,[10] losing Kostolac would mean another big hit for Serbia’s energy production. Environmental impact assessment for TPP Kostolac B3 doesn’t assess the vulnerability of the new power plant to flooding.

References

  1. 1 2 3 4 Potpisan ugovor o izgradnji novog bloka TE “Kostolac“ Ministarstvo rudarstva i energetike, November 20, 2013. Retrieved on 2014-30-07.
  2. Serbia: Ambitious energy investment plan, JV and PPP with foreign partners in new TPP and HPP, the report Serbia Energy, January 1, 2014. Retrieved on 2014-30-07.
  3. Savic, Misha. Serbs Sign $716 Million Coal Plant, Mine Deal With CMEC Bloomberg, November 20, 2013. Retrieved on 2014-30-07.
  4. Gallop, Pippa. Serbian government props up almighty coal Bankwatch, July 2, 2014. Retrieved on 2014-30-07.
  5. 1 2 First court case against coal power plant construction in Serbia Bankwatch, July 2, 2014. Retrieved on 2014-30-07.
  6. Public Procurement Act. Retrieved on 2014-30-07.
  7. Saopštenje za javnost: projekat Kostolac B3 po lupom. CEKOR, April 25, 2014. Retrieved on 2014-31-07.
  8. Kostolac power plant in east threatened by water B92, May 18, 2014. Retrieved on 2014-30-07.
  9. Fight for Kostolac power plant, third embankment put up Tanjug, May 18, 2014. Retrieved on 2014-30-07.
  10. B92. Coal transport from Kolubara to Nikola Tesla power plant resumes. Retrieved 6. 6. 2014
This article is issued from Wikipedia - version of the Wednesday, August 12, 2015. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.