Tehri Dam

Tehri Dam

The dam in 2008
Location of Tehri Dam in India Uttarakhand
Country India
Location Uttarakhand
Coordinates 30°22′40″N 78°28′50″E / 30.37778°N 78.48056°E / 30.37778; 78.48056Coordinates: 30°22′40″N 78°28′50″E / 30.37778°N 78.48056°E / 30.37778; 78.48056
Status Operational
Construction began 1978
Opening date 2006
Construction cost US$1 billion
Owner(s) THDC INDIA LIMITED
Dam and spillways
Type of dam Embankment, earth and rock-fill
Impounds Bhagirathi River
Height 260.5 m (855 ft)
Length 575 m (1,886 ft)
Width (crest) 20 m (66 ft)
Width (base) 1,128 m (3,701 ft)
Spillway type Gate controlled
Spillway capacity 15,540 m3/s (549,000 cu ft/s)
Reservoir
Total capacity 4.0 km3 (3,200,000 acre·ft)
Surface area 52 km2 (20 sq mi)
Power station
Commission date 2006
Type Pumped-storage
Turbines Vertical Francis turbines
Installed capacity 1,000 MW (1,300,000 hp)
Max. planned: 2,400 MW

The Tehri Dam is the tallest dam in India and one of the tallest in the world. It is a multi-purpose rock and earth-fill embankment dam on the Bhagirathi River near Tehri in Uttarakhand, India. It is the primary dam of the THDC India Ltd. and the Tehri hydroelectric complex. Phase 1 was completed in 2006, the Tehri Dam withholds a reservoir for irrigation, municipal water supply and the generation of 1,000 megawatts (1,300,000 hp) of hydroelectricity. The dam's 1,000  MW pumped-storage scheme is currently under construction with expected commissioning in May 2018.[1]

History

Tehri dam in November 2004

A preliminary investigation for the Tehri Dam Project was completed in 1961 and its design was completed in 1972 with a 600 MW capacity power plant based on the study. Construction began in 1978 after feasibility studies but was delayed due to financial, environmental and social impacts. In 1986, technical and financial assistance was provided by the USSR but this was interrupted years later with political instability. India was forced to take control of the project and at first it was placed under the direction of the Irrigation Department of Uttar Pradesh. However, in 1988 the Tehri Hydro Development Corporation was formed to manage the dam and 75% of the funding would be provide by the federal government, 25% by the state. Uttar Pradesh would finance the entire irrigation portion of the project. In 1990, the project was reconsidered and the design changed to its current multi-purpose.[2] Construction of the Tehri Dam was complete in 2006 while the second part of the project, the Koteshwar Dam was completed in 2012.

Technical description

The dam is a 260.5 metres (855 ft) high rock and earth-fill embankment dam. Its length is 575 metres (1,886 ft), crest width 20 metres (66 ft), and base width 1,128 metres (3,701 ft). The dam creates a reservoir of 4.0 cubic kilometres (3,200,000 acre·ft) with a surface area of 52 square kilometres (20 sq mi). The installed hydrocapacity is 1,000 MW along with an additional 1,000 MW of pumped storage hydroelectricity. The lower reservoir for the pumped-storage plant is created by the Koteshwar Dam downstream.

The Tehri Dam and the Tehri Pumped Storage Hydroelectric Power Plant are part of the Tehri Hydropower Complex which also includes the 400 MW Koteshwar Dam.[2] Power is distributed to Uttar Pradesh, Uttarakhand, Punjab, Delhi, Haryana, Jammu & Kashmir, Chandigarh, Rajasthan and Himachal Pradesh. The complex will afford irrigation to an area of 270,000 hectares (670,000 acres), irrigation stabilization to an area of 600,000 hectares (1,500,000 acres), and a supply of 270 million imperial gallons (1.2×10^6 m3) of drinking water per day to the industrialized areas of Delhi, Uttar Pradesh and Uttarakhand. The total expenditure for this project was 1 billion U.S. dollars. The Indian National Trust for Art and Cultural Heritage (INTACH),a cost benefit analysis was commissioned and was concluded that the construction cost of the dam twice the projected benefits.[3]

Scheduling and generation despatch

The Scheduling and Despatch of the Tehri Hydro Power plant is done by Northern Regional Load Despatch Centre which is the apex body to ensure the integrated operation of the power system grid in the Northern region and comes under Power System Operation Corporation Limited (POSOCO). At present, THDC India Ltd. is generating around 3000 million Unit of energy annually from this dam.

The main Power house of Tehri Dam that houses 4 generators each capable of producing 250 MW of power.

Environmental issues

Tehri dam in July 2008

The Tehri Dam has been the object of protests by environmental organizations and local people of the region. In addition to the human rights concerns, the project has spurred concerns about the environmental consequences of locating such a large dam in the fragile ecosystem of the Himalayan foothills. There are further concerns regarding the dam's geological stability. The Tehri dam is located in the Central Himalayan Seismic Gap, a major geologic fault zone. This region was the site of a 6.8 magnitude earthquake in October 1991, with an epicenter 53 kilometres (33 mi) from the location of the dam. Dam proponents claim that the complex is designed to withstand an earthquake of 8.4 magnitude, but some seismologists say that earthquakes with a magnitude of 8.5 or more could occur in this region . Were such a catastrophe to occur, the potentially resulting dam-break would submerge numerous towns downstream, whose populations total near half a million.

A protest message against Tehri dam, which was steered by Sundarlal Bahuguna for years. It says "We don't want the dam. The dam is the mountain's destruction."

The relocation of more than 100,000 people from the area has led to protracted legal battles over resettlement rights, and ultimately resulted in the project's delayed completion.[4]

Since 2005, filling of the reservoir has led to the reduced flow of Bhagirathi water from the normal 1,000 cubic feet per second (28 m3/s) to a mere 200 cubic feet per second (5.7 m3/s). This reduction has been central to local protest against the dam, since the Bhagirathi is considered part of the sacred Ganges whose waters are crucial to Hindu beliefs. At some points during the year, the tampering with Bhagirathi waters means this tributary stops flowing. This has created resentment among many Hindus, who claim that the sanctity of the Ganges has been compromised for the generation of electricity.Though the officials say that when the reservoir is filled to its maximum capacity the flow of the river will again become normal. In spite of concerns and protestation, operation of the Tehri Dam continues.

References

  1. "Projects:Current Status". Tehri Hydro Development Corporation. Retrieved 5 October 2015.
  2. 1 2 Tehri Dam: An Engineering Marvel by: Basistha Raj Adhikari
  3. "IRN FACT SHEET" (PDF). Tehri Dam: 3. October 2002.
  4. Terminski, Bogumil (2013). "Development-Induced Displacement and Resettlement: Theoretical Frameworks and Current Challenges", Indiana University,available at: http://dlc.dlib.indiana.edu/dlc/handle/10535/8833?show=full

External links

Wikimedia Commons has media related to Tehri Dam.
This article is issued from Wikipedia - version of the Saturday, April 02, 2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.