Ulu Jelai Power Station

Ulu Jelai Power Station
Location of Ulu Jelai Power Station in Malaysia
Country Malaysia
Location Cameron Highlands, Pahang
Coordinates 4°27′1″N 101°35′7″E / 4.45028°N 101.58528°E / 4.45028; 101.58528Coordinates: 4°27′1″N 101°35′7″E / 4.45028°N 101.58528°E / 4.45028; 101.58528
Purpose Power, flood control
Status Under construction
Construction began March 1, 2011
Construction cost RM2.4 billion
Owner(s) Tenaga Nasional Berhad
Dam and spillways
Type of dam Gravity dam
Impounds Bertam river
Height 88 m (289 ft)
Length 500 m (1,640 ft)
Width (crest) 3 m (10 ft)
Width (base) 115 m (377 ft)
Spillway capacity 5,000 m3/s (180,000 cu ft/s)
Reservoir
Creates Susu reservoir
Catchment area 0.1 km2 (0.039 sq mi)
Normal elevation 540 m (1,772 ft)
Power station
Type Underground
Hydraulic head

Rated: 330 m (1,083 ft)
Maximum: 335 m (1,099 ft)

Power generation
Nameplate capacity 372 MW
Capacity factor 8%
Annual generation 282 GWh (1,020 TJ) (estimated)
Turbines 2 × 186 MW vertical Francis-type

The Ulu Jelai Power Station is a hydroelectric power station under construction in the district of Cameron Highlands, Pahang, Malaysia. It is one of the entry point projects under the Economic Transformation Programme.[1]

Location

The project is located approximately 150 km north of Kuala Lumpur. The nearest town is Ringlet, 40 km away. The under-construction station is accessible from route 194 connecting the tows of Ringlet and Sungai Koyan. It is located within Ulu Jelai and Bukit Jerut forest reserves, near Cameron Highlands-Lipis district border.

Construction

Construction commenced in 2011 and with the first unit expected to be commissioned in December 2015. A 88 m high roller compacted concrete dam has been built on Sungai Bertam, impounding the Susu reservoir. 15 km long water transfer tunnels are used to divert water from Sungai Telom and Sungai Lemoi. Other underground structures include headrace and tailrace tunnels, surge shaft, two penstocks, transformer and surge chamber caverns. It has an underground power house with generating capacity of 2 x 186 MW. Water used for electricity generation will be released back into Sungai Telom.

Construction of the water transfer tunnels were performed using a 3 m diameter tunnel boring machine. The drill and blast technique was employed for the excavation of the underground power house, transformer and surge chamber caverns, headrace and tailrace tunnels and penstocks. The surge shaft was excavated using the raised boring technique.

Apart from the construction of the structures for power generation, this project requires the relocation of 3 orang Asli villages, namely Kampung Susu, Kampung Tiat and Kampung Pinang.

Issues

Sedimentation is a major issue for Sungai Bertam and Sungai Telom.[2] A check dam is currently under construction at the tail of Susu reservoir on Sungai Bertam to reduce the amount of sediment entering. A desander system has also been constructed at the intake of Sungai Telom for the same purpose.

See also

References

  1. Pemandu. "Tenaga Nasional Infrastructure Investment".
  2. Isabell Lai (2013-05-19). "Hills 'raped' at an alarming rate". Star Publications (M) Bhd. Retrieved 2015-10-14.
This article is issued from Wikipedia - version of the Saturday, October 24, 2015. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.