M1 (İzmir Metro)

Fahrettin Altay-Evka 3 Line
Overview
Owner İzmir Metro A.Ş.
Locale İzmir
Transit type Rapid transit
Number of lines 1
Number of stations 17
Operation
Began operation 2000
Operator(s) İzmir Metro
Technical
System length 20.1 km (12.5 mi)
Track gauge 4 ft 8 12 in (1,435 mm) standard gauge

The M1 (İzmir Metro) or Fahrettin Altay-Evka 3 Line is an 20.1 km long route of the Izmir Metro. It is the only line on the system but new lines are also under construction.[1]

Stations

View of Stadyum Station from outside
View of Bölge Station from inside
Station Opening Structure Construction Structure Platform Tracks
Fahrettin Altay 27 July 2014 Cut-and-Cover Tunnel 2 Side Platforms 2
Poligon 27 July 2014 Cut-and-Cover Tunnel 2 Side Platforms 2
Göztepe 25 March 2014 Deep Tunnel 2 Side Platforms 2
Hatay 29 December 2012 Cut-and-Cover Tunnel 2 Side Platforms 2
İzmirspor 29 December 2012 Cut-and-Cover Tunnel 2 Side Platforms 2
Üçyol 22 May 2000 Deep Tunnel 2 Side Platforms 2
Konak 22 May 2000 Cut-and-Cover Tunnel 1 Island Platform 2
Çankaya 22 May 2000 Cut-and-Cover Tunnel 1 Island Platform 2
Basmane 22 May 2000 Cut-and-Cover Tunnel 1 Island Platform 2
Hilal 22 May 2000 Viaduct 2 Side Platforms 2
Halkapınar 22 May 2000 Grade 2 Island Platforms 3
Stadyum 22 May 2000 Viaduct 2 Side Platforms 2
Sanayi 22 May 2000 Grade 1 Island Platform 2
Bölge 22 May 2000 Grade 1 Island Platform 2
Bornova 22 May 2000 Splitting Tunnel 1 Island Platform 2
Ege Üniversitesi 30 March 2012 Cut-and-Cover Tunnel 2 Side Platforms 2
Evka 3 30 March 2012 Cut-and-Cover Tunnel 2 Side Platforms 2

Connections

At Basmane, Hilal and Halkapınar stations, there are connections available to Turkish State Railways.

References

  1. "Izmir Metro" (PDF). 2009. Retrieved 12 June 2010.

See also

This article is issued from Wikipedia - version of the Friday, April 29, 2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.