Godavari Bridge

Godavari Bridge

The Godavari Bridge across Godavari River
Coordinates 16°59′52″N 81°45′21″E / 16.99778°N 81.75583°E / 16.99778; 81.75583Coordinates: 16°59′52″N 81°45′21″E / 16.99778°N 81.75583°E / 16.99778; 81.75583
Carries Two lanes of Road and Single Railway line.
Crosses Godavari River
Locale Rajahmundry
Other name(s) Rajahmundry-Kovur Bridge
Preceded by The Havelock Bridge
Followed by Godavari Arch Bridge
Characteristics
Design Truss Bridge
Total length 4.2 kilometres (2.6 mi)
Longest span 97.5 metres (320 ft)
History
Engineering design by Braithwaite, Burn & Jessop Construction Company
Opened August 16, 1974

The Godavari Bridge or Kovvur-Rajahmundry Bridge is truss bridge spanning Godavari river in Rajahmundry, India. It is Asia's third longest road-cum-rail bridge crossing a water body, after the Sky Gate Bridge in Kansai International Airport, Osaka and Ganga rail–road bridge in Patna, Bihar, India. It is second of the three bridges that span the Godavari River at Rajahmundry. The Havelock Bridge being the earliest, was built in 1897, and having served its full utility, was decommissioned in 1997. The latest bridge is the Godavari Arch Bridge, a bowstring-girder bridge, built in 1997 and presently in service.

The bridge is 4.2 kilometers (2.7 km Rail & 4.2 km Road) long consisting of 27 spans of 91.4 m and 7 spans of 45.72 m of which 6 spans of 45.72m are in 6 deg. curve at long Rajahmundry end to make up for the built up area. The bridge has a road deck over the single track rail deck, similar to the Grafton Bridge in New South Wales, Australia. This bridge, in addition to Godavari Arch Bridge, has been widely used to represent Rajahmundry in arts, media, and culture. It is one of the recognised symbols of Rajahmundry.[1]

Geography

The road-cum-rail bridge is built across the Godavari River (largest river in South India at over 1,000 kilometres (620 mi) length) as it enters into the deltaic reach before debouching into the sea 60 kilometres (37 mi) downstream of the bridge, the second largest river in India. At the location of the bridge, near Rajahmundry, the river flows with a width of about 2.7 kilometres (1.7 mi), split in two channels with an island formation in between. The maximum discharge observed in the river is reported to be around 3 million m3/s and the maximum velocity of water flow as 5 metres (16 ft) per second

History

Construction

During the Third Five-Year plan doubling of railway track between Chennai-Howrah was planned. Most of the route had been doubled except the small stretch of track between Kovvur- Rajahmundry where a bridge had to be built to span the three kilometer long Godavari River. During 1964, the construction of second bridge across Godavari river at Rajahmundry was sanctioned as a part of doubling of track between Kovvur- Rajahmundry. But there had been a persistent demand from local population for construction of a road link between Kovvur- Rajahmundry, which would essentially link East Godavari and West Godavari districts. The Andhra Pradesh State Government came forward with the proposal to add a road deck over the rail bridge under construction as a part of doubling the railway track between Chennai-Howrah.[2]

It was commissioned by South Central Railway division of Indian Railways. Construction of the bridge began in the early 1970s by Braithwaite, Burn & Jessop Construction Company, a group company of Bharat Bhari Udyog Nigam Limited.[3] When completed it was Asia's longest rail -cum- road bridge.

It was inaugurated by the then President of India, Fakhruddin Ali Ahmed in 1974.

Sister bridges

Old Godavari bridge

The Old Godavari Bridge or Havelock Bridge was built in 1900 by Mr.F.T.G.Walton, now decommissioned, this bridge has 56 spans and is 2754 m long. It was constructed with stone masonry and steel girders and certainly a marvel of British engineering. The New Godavari Bridge was made as a substitute for it.

Godavari arch bridge

Godavari Arch Bridge is the newest bridge constructed among the three. Constructed by the Hindustan Construction Company (HCC), this bridge is a modern day engineering feat. The bridge is made of bow string girder arches. The bridge is fit for 350 km/h rail services. The bridge was opened for rail traffic in 2003.

Panorama

See also

Gallery

Wikimedia Commons has media related to Godavari Bridge.

References

  1. http://www.thehindubusinessline.in/2006/03/06/stories/2006030601050500.htm
  2. R.R., Bhandari. Bridges: A Spectacular Feat of Indian Engineering (PDF).
  3. "Structurae - Godavari Bridge". Structurae. Retrieved 9 June 2011. |first1= missing |last1= in Authors list (help)