The Harmon
The Harmon | |
---|---|
Alternative names |
The Harmon Hotel & Residences Project CityCenter Lifestyle Hotel Project CityCenter Block C - North Tower |
General information | |
Status | Demolished |
Type | Hotel |
Address |
3720 Las Vegas Boulevard Las Vegas, Nevada 89109 United States |
Coordinates | 36°06′31″N 115°10′25″W / 36.108681°N 115.173611°WCoordinates: 36°06′31″N 115°10′25″W / 36.108681°N 115.173611°W |
Construction started | 2007 |
Completed | 2009 |
Opening | Never |
Demolished | 2015 |
Owner |
MGM Mirage Dubai World |
Landlord | MGM Resorts International |
Height | ~138 m (453 ft) |
Technical details | |
Floor count | 28 |
Floor area | 231,900 m2 (2,496,000 sq ft) |
Design and construction | |
Architecture firm | Foster + Partners |
Other designers | MGM Mirage Design Group |
Main contractor |
Perini Building Company Tishman Construction |
Other information | |
Number of rooms | 400 |
References | |
[1][2][3] |
The Harmon was a highrise building at the CityCenter Las Vegas development in Paradise, Nevada. The tower was designed by Foster + Partners as a non-gaming boutique hotel, and was to be operated by Andrew Sasson's The Light Group upon completion. The building featured an elliptical layout and highly reflective exterior located on the northeast corner of the project at the intersection of Las Vegas Boulevard and Harmon Avenue. Serious construction defects to the building were discovered in 2008, and the project was halted indefinitely. On August 23, 2013, a Clark County court approved the tower's demolition.[4] The dismantling of the tower began in the summer of 2014 and completed in the fall of 2015.[5]
History
At the beginning of the project, the hotel was called the "Lifestyle Hotel" and then "The Harmon Hotel, Spa & Residences". The tower was planned to have 400 hotel rooms and approximately 207 condominium residences from 800 to 2,900 sq ft (74 to 269 m2) on 49 floors. The hotel's pool deck was planned to be on the roof high above the Las Vegas Strip.[6][7] The exterior of the building was finished in 2009 but the interior work to correct the construction issues was to continue into 2010.
Project scope reduction
In late 2008, work on the Harmon Hotel/Condo Tower was stopped after inspectors discovered construction defects: county inspectors discovered improper installation by Pacific Coast Steel, of critical steel reinforcements (rebar) after 15 stories of the building had already been erected.[8] The error caused a major change in the building's design; instead of being 49 stories, it was reduced to 28 stories with the condominium element, The Harmon Residences removed entirely.[9] At the time, 88 of the 207 condominiums were reserved by buyers who had put 20 percent down. Those buyers were offered refunds or the option to buy in other buildings.[8] Due to the delay and alterations to the design, the building was delayed past the other CityCenter projects and was scheduled to be finished in late 2010 [8][9] but was delayed indefinitely.[10] The canceled units ranged in size from 980 to 3,700 square feet (91 to 344 m2).[11] With litigation pending due to the defects, construction was halted,[12] and MGM Resorts International, the owner of CityCenter, targeted the building for complete demolition.[13]
On July 11, 2011 a report was released by Weidlinger Associates, an engineering firm hired by MGM Resorts International. This report indicated that the building was likely to collapse in a major earthquake and that a determination of possible repairs would take at least a year.[14] On August 15, 2011 MGM announced plans to implode the building.[15]
The hotel's demolition was approved by a judge in August 2013, as the building represented a threat to public safety due to the risk of collapse in an earthquake.[16] Dismantling of the hotel began in June 2014 and is expected to last throughout 2015.[17] The dismantling is expected to cost $11.5 million.[18]
In the fall of 2014 a large and complex legal dispute between CityCenter and the hotel's builders started. Each side has accused the other of breaching their contract and is seeking damages as high as $400 million. The trial was expected to last a year.[19]
Gallery
-
Construction progress in June 2007
-
Construction progress in February 2009
-
Construction progress in July 2009
-
Construction progress in October 2009
-
Construction progress in November 2009
-
-
Photo of the south east side after the exterior is completed
-
Progress demolishing the hotel in November 2014
-
Site of the former hotel in November 2015
References
- ↑ The Harmon at Emporis
- ↑ The Harmon at SkyscraperPage
- ↑ Jennifer Robison (2 December 2009). "CityCenter wow-inspiring". The Las Vegas Review-Journal. Retrieved 25 August 2011.
- ↑ Tony Illia (11 Sep 2013). "Hotel's Razing and Defects Trial Could Be Best Shows in Las Vegas". ENR. Retrieved 12 Sep 2013.
- ↑ http://www.reviewjournal.com/business/casinos-gaming/unfinished-harmon-hotel-demolished-piece-piece
- ↑ Arnold M. Knightly (30 June 2009). "Harmon inspectors blame breakdowns in communications for problems". The Las Vegas Review-Journal. Retrieved 25 August 2011.
- ↑ Joan Whitely (25 July 2009). "The Strip: Harmon Hotel inspector hit hard". The Las Vegas Review-Journal. Retrieved 25 August 2011.
- 1 2 3 Steve Friess (11 February 2009). "Tower Rising in Las Vegas but Now, Not So High". The New York Times. Retrieved 25 August 2011.
- 1 2 Joe Brown (8 February 2009). "Adaptation or ‘disaster’?". The Las Vegas Sun. Retrieved 25 August 2011.
- ↑ Tony Illia (12 April 2010). "MGM Mirage delays Veer, Harmon completion". Las Vegas Business Press. Retrieved 25 August 2011.
- ↑ Aaron Auxier (2011). "The Harmon Residences (canceled)". Vegas Condo Scene. Retrieved 25 August 2011.
- ↑ Arnold M. Knightly (4 May 2010). "Perini tries to enlist aid of governor's office in CityCenter payment". The Las Vegas Review-Journal. Retrieved 25 August 2011.
- ↑ Howard Stutz (13 November 2010). "Unfinished building tied up in litigation until 2012". The Las Vegas Review-Journal. Retrieved 25 August 2011.
- ↑ GARCIA, OSKAR (12 July 2011). "Engineer: Harmon in Vegas would collapse in quake". Buisnessweek. The Associated Press. Retrieved 10 November 2015.
- ↑ Oskar Garcia (15 August 2011). "MGM Resorts seeks county OK to implode defective Harmon hotel tower at CityCenter in Las Vegas". KLAS-TV. The Associated Press. Retrieved 25 August 2011.
- ↑ Jones, Jay (27 August 2013). "Las Vegas: Never-opened Harmon Hotel can be demolished, judge rules". Los Angeles Times.
- ↑ Illia, Tony (9 May 2014). "Court Approves Demolition of Foster + Partners' Harmon Hotel in Vegas". Architectural Record.
- ↑ http://www.reviewjournal.com/business/casinos-gaming/unfinished-harmon-hotel-demolished-piece-piece
- ↑ Geer Thevenot, Carri (October 26, 2014). "Yearlong Harmon Hotel defects trial to start". Las Vegas Review-Journal. Retrieved February 15, 2016.