Kochi Metro

This article is about the elevated metro rail system. For the urban agglomeration, see Kochi metropolitan area.
Kochi Metro
കൊച്ചി മെട്രോ
Overview
Native name കൊച്ചി മെട്രോ
Locale Kochi, Kerala, India
Transit type Rapid transit
Number of lines 1
Number of stations 23
Chief executive Elias George, MD
Headquarters 8th Floor, Revenue Tower, Park Avenue, Kochi[1]
Website Kochi Metro
Operation
Operation will start 1 November 2016
Operator(s) Kochi Metro Rail Ltd. (KMRL)
Train length 3 coaches[2]
Headway 5 minutes[2]
Technical
System length 25.612 km (15.915 mi)
Track gauge 1,435 mm (4 ft 8 12 in) standard gauge[3]
Electrification Third rail 750 V DC[4]
Average speed 34 km/h (21 mph)[2]
Top speed 80 km/h (50 mph)[2]

Kochi Metro is an under-construction metro system for the city of Kochi in Kerala, India. The first phase is being set up at an estimated cost of 5181 crore (US$770 million),[5] and is expected to be completed by 7 June 2016.[6]

Planning

The Route Map of Proposed Phase 1 of Kochi Metro Rail Network View at OpenStreetMap

The Kerala government hoped the Centre would approve a funding structure similar to that used for the Delhi Metro, but they were turned down.[7] The Union Government supported using public–private partnership (PPP) on the build-operate-transfer model.[8] The LDF state government wanted it to be in public sector, which was not accepted to the Central Government. The victory of the United Democratic Front (UDF) in the 2011 Kerala legislative assembly elections, changed the scenario in the state[9] and it was decided that the Kochi Metro would follow the Chennai Metro and Delhi Metro models, and would be implemented on a joint venture basis, with investments by the Central and State Government. A Cabinet decision was taken to form a special purpose vehicle (SPV) called Kochi Metro Rail Ltd. (KMRL) as per orders from Planning Commission and the Union Government for the implementation, operation and maintenance of the metro project.[10]

The Public Investment Board (PIB) cleared the project on 22 March 2012 subject to final approval by the Union Cabinet.[11] The Union Government's share of the cost would be 20.26%, or 1002.23 crore (US$150 million).[12] On 28 March 2012, at a KMRL board meeting, the decision was taken to entrust the Kochi Metro rail project work to the DMRC. The number of metro stations on the line was set at 22.[13][14] On 3 July 2012, Union Government gave final clearance to the project. Then Managing Director of KMRL, Tom Jose said, "Now we will sit down with our valued partner, DMRC, and chalk out the way forward, obtaining advice and guidance from former DMRC Chief, E Sreedharan. We aim to complete the project within a span of 3 to 4 years." [15]

On 14 August 2012, the state government reconstituted the Board of Directors of KMRL. Power Secretary Elias George was appointed as the new Managing Director, replacing Tom Jose. It is believed that Jose's differences with Sreedharan led to the decision.[16][17] Chief Minister Oommen Chandy stated that it was part of administrative decision. The rest of the board would include the Chief Secretary, Finance Secretary and Water Resources Principal Secretary.[18]

The Director Board of Kochi Metro Rail Limited entrusted MD, KMRL to find alternate funding options for the project as advised by DEA (Department of Economic Affairs). As part of it, representatives of the French Development Agency (AFD) met the KMRL team as part of their pre-appraisal mission on 18–19 March 2013. The agency had detailed discussions with KMRL MD Elias George and other senior officials. They also visited the project alignment from Aluva to Petta to understand the project better. Mme. Aude Flogny, Regional Director, South Asia & Mr. Gautier Kohler, Project Coordinator India were there in the team.[19][20] Based on the inputs received from the pre-appraisal mission team of AFD, a formal detailed- appraisal mission team visited Kochi from 25–27 April 2013. The team included Senior Transport Expert of AFD, Mr. Xavier Hoang; AFD regional director for South Asia, Aude Flogny and Project Coordinator, Gautier Kohler. The team inspected the project site and held discussions relating to the funding for Kochi Metro Rail project. Kochi Metro Rail Limited is hoping to get a final commitment from the French financial agency AFD - Agence Française de Développement by the end of December 2013. AFD has stated that they could provide a loan of up to 130 million Euros which is around Rs. 10 billion. The next team from AFD is expected to be here in Kochi to evaluate the project during the month of September, 2013.

On 4 April 2013, KMRL's Director Board signed a contract with the DMRC.[21] The 22 proposed stations for the Kochi Metro were approved by the State Cabinet on 19 June 2013.[22]

DMRC will have to get the approval of KMRL if it wants to significantly deviate from the technical specifications.[23]

Controversy over DMRC's role

In December 2011, Kerala Minister for Public Works V.K. Ebrahim Kunju announced that the work would be offered by global tender. DMRC MD E. Sreedharan said he would not be interested in participating unless the DMRC was involved.[24] Citing the examples of metros in Bangalore and Chennai, he said, "They decided to take up the work on their own but had to depend on the DMRC for many things. I did not want Kochi to make the same mistake."[25]

On 3 January 2012, Chief Minister Oommen Chandy stated that E. Sreedharan would have final say on the metro project.[26]

Aryadan Mohammed, Minister for Power and Transport and the Vice Chairman of Existing Board of Directors, said that the Kerala Government had decided as early as in March 2010 that Sreedharan would be in charge of the project. "There are no doubts about this. It was the Kerala Cabinet which had taken this decision and there would be no change in it," he said.[27]

Some government ministers and IAS officials alleged that Central Vigilance Commission (CVC) norms do not allow awarding of contract to an agency which did the consultancy for a project.[28] However, DMRC principal adviser E. Sreedharan has stated that the CVC norms would not apply in this case, as the contract is between two government agencies. Another issue for the metro was that DMRC had to obtain permission of its director's board to undertake projects outside Delhi.[29]

On 8 January 2013, following a high level meeting attended by Chief Minister Oommen Chandy, Minister of Overseas Indian Affairs Vayalar Ravi, Union Minister K.V. Thomas, DMRC Principal Advisor E. Sreedharan, Union Urban Development Secretary Sudheer Krishna, Chief Secretary Jose Syriac, KMRL MD Elias George, DMRC MD Mangu Singh, Union Minister for Urban Development Kamal Nath officially confirmed that DMRC would undertake the work of Kochi Metro.[30]

Support for DMRC

The Corporation of Cochin and Kochi Mayor Tony Chammany supported handing over work to DMRC. The Mayor launched a campaign promoting DMRC on his Facebook page. The Mayor also launched a website on 24 October 2012.[31] Chammany had stated that, "Government of Kerala and the Corporation of Cochin along with the people of Kerala unanimously want the Delhi Metro Rail Corporation to take up the work of Kochi metro which will be crucial to the growth and development of Cochin City."[32] Opposition parties in the state, on several occasions, expressed support for the DMRC and alleged that corruption and delays would occur in the project if it was not handed to DMRC. JICA asked the KMRL to ensure the support of DMRC on 1 December 2012. Takeshi Fukayama of JICA said, "DMRC has an expertise in implementing the project and so, KMRC should take their support in executing the project. KMRC should use the expertise of DMRC for implementing the project."[33][34]

Public support was overwhelmingly in favour of DMRC and Sreedharan. On 27 October 2012, Kochiites formed a 25 km human chain from Aluva to Petta, demanding work be handed over to DMRC. The protest was organized by the City Development Committee.[35][36]

Preparatory work and supporting activities

The DMRC felt that it was necessary to undertake preparatory works to avoid disruptions to commuters during the construction of the Kochi Metro. The agency suggested five preparatory works to the State government, which approved all five projects in March 2010. The preparatory works were intended to be completed before constructing the metro.[37] The works included the widening of 3 arterial roads and the construction of a new rail overbridge (RoB) near KSRTC station and a foot overbridge.[38][39] The A.L. Jacob RoB near the KSRTC stand, commissioned on 12 May 2013, was the first of the five works to be completed. Apart from the five originally proposed projects, some additional projects such as the construction of the Ernakulan North RoB,[37] and the flyover at Edapally were also carried out.

The work was being undertaken by DMRC initially but was later undertaken by KMRL, due to a shortage of qualified personnel with the DMRC.[40] Other projects include construction of a new RoB connecting Mullassery Canal Road and Salim Rajan Road, and the widening of the Town Hall-Madhava Pharmacy Junction stretch, and Jos Junction-South Railway Station road.[41] The DMRC will execute all preparatory works. The State Government had set apart 1.58 billion for preliminary works. On 3 March 2012, KMRL handed over 150 million to DMRC for undertaking the preparatory works. The DMRC had been given 230 million earlier.[42][43][44][45] The DMRC will also build a 1.35 billion (US$20 million) flyover at Edappally.[46]

A.L. Jacob RoB

A.L. Jacob Railway Over Bridge on Salim Rajan Road

An overbridge on Salim Rajan road was planned to be built before commencement of work on the metro itself. Construction of the bridge began in October–November 2011,[47][48][49] and was opened to the public on 12 May 2013.[50] On the same day, Chief Minister Oomen Chandy announced that the bridge would be officially named A.L. Jacob RoB.[51][52][53][54][55]

Road widening and resurfacing

The 450-metre Ernakulam Town Hall-Madhava Pharmacy Junction stretch in Banerjee Road had been widened to a 22 metre wide, 4-lane road by the end of July 2013.[56] A total of 56 cents of land had to be acquired in the stretch. The work is estimated to cost 90 million (US$1.3 million).[56]

Delays in widening the Vyttila – Petta road affected work on the metro's fourth reach, with contractor Era Infra Engineering unable to start work,[57] until mid-November 2013.[58]

For the purpose of traffic diversion, KMRL resurfaced 21 roads in and around the city. Kerala Construction Corporation did the work with five-year guarantee using BMBC specifications for a cost of 16.31 crore (US$2.4 million). KMRL also recruited traffic wardens in different part of the city to help police to control traffic.[59]

Flyover at Edappally

KMRL and the Kerala Public Works Department (PWD) signed an agreement on 22 July 2013, to build an 1.08 billion (US$16 million) flyover at Edapally[60] to reduce the congestion at the junction of NH 47 and NH 17 at Edappally.[61] The DMRC was appointed to implement the project. Construction on the flyover was inaugurated by Works Minister V.K. Ebrahim Kunju on 21 November 2013, and is expected to be completed in two years.[47][48]

Other works

Pachalam RoB

On 21 February 2014, the Kerala High Court expressed its displeasure over the failure of the Kochi Corporation to finalise the final alignment of the proposed rail over bridge (ROB) at Pachalam submitted by the Roads and Bridges Development Corporation. The Division Bench comprising Chief Justice Manjula Chellur and Justice A.M. Shafeeque directed the corporation to place on record the final alignment of the ROB by 2 April 2014. The Bench observed that the civic body had "not moved an inch", after the discussion on the alignment submitted by the Roads and Bridges Development Corporation in 2011.[62]

The Pachalam RoB was approved in-principle by the Kochi Corporation on 10 February 2014.[63] The RoB received approval from the State Cabinet on 26 February.[64] The 2-lane, 10-metre wide RoB is estimated to cost 520 million, and will be constructed by the DMRC.[63] About 52 cents of land will be acquired for the project.[65]

The foundation stone for the project was laid on 4 March,[66] and construction was expected to complete in 6 months.[67] It was inaugurated on 11 January 2016

Shifting Vytilla station

Based on suggestions from Centre for Public Policy Research (CPPR), Cochin, Kochi Metro Rail Limited decided to shift Vyttila station to Vyttila Mobility Hub to follow the guidelines of ministry of Urban Development to integrate various mode of transport.[68] Long distance buses operate out of Vyttila hub and the hub authorities are planning to build a new boat jetty there as the part of their second phase of development. Thus, the Kochi metro project became the first metro in the country which connects rail, road and water transport facilities.[69]

New KSRTC parking lot

A parking lot at Karakkamuri was provided to KSRTC, when KMRL took over the parking space to carry out preparatory works associated with Kochi metro project. In return for the land used for Salim Rajan RoB KMRL reconstructed the inspection ramp for KSRTC.[70] But, as rains started, the new parking lot became murky with slush and mud and it became difficult for drivers to drive out vehicles resulting in creation of traffic blocks in the city. Following KSRTC's complaint, KMRL handed over the task of relaying the ground to KSCC for a budget of 55 lakh (US$82,000).[71]

Thevara-Perandoor canal cleaning

Water logging is a major problem in Kochi, and is the main cause damage to the roads in the city. The uninterrupted flow of water through the canals is the best way to prevent the water logging in the city. To ensure the smooth traffic in the city, KMRL cleaned the Thevara– Perandoor Canal, a major canal of Kochi. The cleaning work contracted to the Kerala Shipping and Inland Navigation Corporation (KSINC) for an amount of 2.62 crore (US$390,000).[72]

Land Acquisition

The total amount of land required for the project is 40.409 hectares. The total land required for all stations is 9.3941 hectares, including area required for parking lots. Aluva, Pettah, Kalamassery, Edappally and Kaloor stations will have larger parking areas requiring about 2.7869 hectares of land. The coach depot at Muttom requires 23.605 hectares of land, higher than the originally estimated 17 hectares.[73][74][75][76] Approximately, 4.6 hectares of land will be required for widening curves and stretches where the metro's viaduct is positioned outside the median. Apart from the above, 102.50 cents of land is required for preparatory works, and 94 hectares in Muttom and 20 hectares of land in Kakkanad is to be acquired for developing the land for commercial use.[77]

The original plan was to acquire about 31.9216 hectares of land in Ernakulam, Elamkulam, Poonithura, Thrikkakara North, Edappally South and Aluva West. Out of this approximately, 17 hectares was for the Muttom coach maintenance depot. The remaining land was required for the construction of metro stations. Approximately, 15 hectares out of the required 31.92 was government owned land. However, the land required for parking at stations, road widening and straightening curves along the alignment were not assessed in the original plan.[78] The addition of parking lots increased the amount of land required by 8.4874 hectares.

The district-level purchase committee fixed the maximum compensation for land acquisition at 5.2 million per cent for the land to be acquired for preparatory works. The district administration can take ownership of land only after paying at least 80% of the price. Land acquisition for a foot overbridge near the KSRTC main depot will cost 2.8 million per cent and land for the approach road of the Ponnurunni railway overbridge will be acquired at 1850,000 per cent. The prices have been approved by the State Empowered Committee.[79][80] The total estimated cost of land acquisition is 11.10 billion., higher than the 6.72 billion estimated as per the original plan.[81][82]

The Kadavanthra station will be built on the land which housed GCDA's Nandanam park near the canal. Part of the land required was obtained from the Greater Cochin Development Authority on 13 February 2014.[83] The remaining land was owned by the KSEB, and was acquired separately.[84]

When the Railways demanded 3 billion for a 35-year lease of 4,360 square metres of land intended as the location of Ernakulam South metro station and other facilities, KMRL officials rejected the offer, as 3 billion worked out to about 8% of the metro project's total cost. The station was instead built on land owned by the Kochi Corporation near Ernakulam Girls' High School, while the Operations Control Centre was built in Muttom. The cost for the station was 100 million.[85]

Then District Collector M.G. Rajamanikyam announced on 7 March 2014 that land acquisition would take another three months.[86][87]

Construction

Prime Minister Manmohan Singh laid the foundation stone for the project on 13 September 2012.[88][89][90] Construction work on the Kochi Metro rail project began on 7 June 2013,[54] with the piling works for the viaducts near Changampuzha Park, after an official launch ceremony held at the Jawaharlal Nehru Stadium at 10:30am on the same day.[91][92][93][94] At the inauguration ceremony, the State Government announced that the metro would be extended a kilometre-and-a-half from Pettah to Tripunithura,[95] Construction work on metro's first station, at Kaloor, began at 10:30am IST on 30 September 2013, when Soma Constructions began piling.[96][97] The next station were piling work was carried out was Aluva.[98]

Several companies (Era Infra Engineering, Larsen & Toubro, and Soma Constructions) were contracted to build viaducts and stations.[99][100][101] Larsen and Toubro (L&T) was awarded the contract to construct the viaduct and 6 stations on the Kalamassery-Stadium stretch[102] in April 2013 at an estimated cost of 4 billion (US$59 million).[103]

Some utilities along the planned route will have to be moved.[104] About 4.5 to 500,000 cubic metres of sand will be required for construction of the metro. It is planned to source the sand from rivers in Kerala, while using imported and/or manufactured sand is another option.[105]

The project will require 477 trees to be cut. DMRC has promised that it will plant 10 trees for each one it has to remove.[106][107] The tree planting program was launched on 21 June 2013, with 500 saplings planted by local students.[108] However, the saplings planted at the HMT land near Kalamassery, died due to a lack of proper care. KMRL plans to hire another agency to care for the trees.[109]

According to E. Sreedharan, the DMRC has set internal targets for the construction.[110] It aims to complete the 13 km Aluva-Palarivattom stretch by December 2015, and the remaining 12 km Palarivattom-Pettah stretch by March 2016.[111] The Chief Minister's target for completion of metro work was 1,095 days, however, the Sreedharan set DMRC staff the goal of completing it in 939 days.[112]

The metro's civil works faced some initial delays because of rain, labour issues, etc. but picked up towards end of 2013. Construction was expected to be carried out quickly until May, when it was expected to slow down again due to monsoon.[113]

Transport Minister Aryadan Mohammed stated on 14 December 2013 that he had asked the DMRC to replace Era Constructions, the contractor of the metro's fourth reach (Vytilla-Pettah), because the work was going too slowly. Mohammed stated that the DMRC would make the final call on replacing the contractor.[114] Construction of the South-Pettah stretch was slow partly due to a labour dispute.[113] By the end of December, DMRC officials announced that Era Constructions would be replaced. The New Indian Express quoted a DMRC official as saying, "The work of the Era has been found to be extremely unsatisfactory. They also do not have the financial capacity to go ahead with the contract, especially because Ranken, their Chinese partner, is not aiding them. The DMRC will call for re-tender for the work between South and Vyttila. We have asked Era Constructions to go ahead with the work at Vyttila."[115] Soma Constructions began preliminary work on the 1.6 km long South overbridge-Elamkulam reach[116][117] on 16 January.[118] The estimated cost of the works from South to Vytilla is 1.50 billion.[116]

Since the launch of the project 7 June 2013, the project has been delayed by bad weather, land acquisition problems, and labour disputes.[119] The DMRC said, "Most workers who owe allegiance to the unions are unskilled, but have to be paid wages equal to or more than that is paid to the skilled work force deployed by contractors. This is affecting the pace of works and the work culture."[120]

Sreedharan said on 4 March 2014 that the commissioning of the Kochi Metro would be delayed stating, "Owing to delays in land acquisition, the work on Metro rail can only be completed partially within the stipulated time. Road widening and land acquisition on the stretch between Vyttila and Pettah junctions have not been completed yet. This will delay completing the work on that stretch. We will be able to complete the work from Aluva to MG Road in the stipulated time."[121]

The first 'U' shaped concrete girder of the Kochi Metro Rail was successfully installed on Saturday 12 July 2014 early morning.The girder was installed at Pulinchode near Aluva. The ‘U- shaped’ girder was cast at the Metro Casting Yard at Kalamassery. It was transported from the yard around 7 pm on Friday with the help of two huge cranes and special trailers brought from Mumbai.[122]

Viaduct under construction at Kalamassery

The girder reached the site at midnight, and was installed with the help of cranes having capacities of 350 tonne and 400 tonne.

The first test run of the Kochi metro was conducted on 27 February 2016 on a 1 km section between Muttom Yard depot and Kalamassery at speeds of up to 10 km/h.[123]

Extension to Tripunithura

Following a string of protests, KMRL decided to extend the metro's terminal from Pettah to Tripunithura in phase one of the project.[124]

KMRL approved the extension of the metro to Tripunithura on 27 January 2014. Speaking to the media after the meeting, Union Urban Development Secretary and KMRL chairman Sudhir Krishna announced that the 2 km extension would cost an additional 3.23 billion (US$48 million). The extension will add two more stations, near Alliance Junction and SN Junction, to the line.[125] The extension will be completed after the Aluva-Pettah stretch.[126] The State Cabinet approved the Tripunithura extension on 5 March 2014, based on the preliminary RITES report.[127]

Funding

The original cost of the Kochi Metro project was 51.46 billion (US$760 million),[128] but this later increased to 55.373 billion (US$820 million).[129][130] Taxes on the project will come to about 2.373 billion (US$35 million) which will be borne by the Kerala Government along with any escalations.[131][132] JICA has agreed to offer loan at an interest rate of 1.50%.[133] The total estimated cost of land acquisition is 11.1 billion (US$160 million), higher than the 6.72 billion (US$100 million) estimated as per the original plan.[81][82][132] The total external borrowing requirement for the metro rail project is nearly 21.7 billion (US$320 million).[134]

On 4 November 2013, the KMRL director board approved an offer from Canara Bank to provide it a loan of 11.7 billion (US$170 million).[135] KMRL signed an agreement with French financial aid agency Agence Francaise de Development (AFD) on 8 February 2014, to provide a 15.25 billion ( 180 million) loan for the project. The AFD loan is for a period of 25 years at the rate of 2% interest. The period is composed of a 20-year repayment period and a five-year grace period.[136][137] The Centre and state governments contributed 7.53 billion (US$110 million) each as equity share for the project.[134] The line is expected to break even in 2023.[138]

KMRL signed a term loan agreement for Rs 1,170 crore with Canara Bank on 20 July 2014.[139] The Metro authority said that Canara Bank has taken this project as a special case with their request of interest reduction and provided relaxations on their conditions. The Canara Bank chairman and managing director R K Dubey assured support to various infrastructure projects undertaken by the state government including “Kannur Airport and other projects being implemented in Thiruvananthapuram and elsewhere in the state”.[140]

Network

Proposed Kochi Metro Route Map

Aluva
Pulinchodu
Infopark - II
Companypady
Infopark - I
Ambattkavu
Rajagiri
Muttom
Chittethukara
North Kalamassery
Kochi SEZ
CUSAT
Kakkanad Junction
Pathadippalam
Kunnumpuram
Edappally Junction
Vazhakkala
Changampuzha Park
Chempumukku
Palarivattom
Palarivattom Bypass
Nehru Stadium
Nehru Stadium
Kaloor
Lissie
M G Road
Maharajas College
Ernakulam Junction
Kadavanthra
Elamkulam
Vyttila Mobility Hub
Thykoodam
Pettah
Alliance Junction
SN Junction
Thripoonithura Station

KMRL has proposed an elevated route spanning 25.253 km (15.691 mi) from Aluva to Petta with 23 stations.[141] All platforms will be 70 metres (230 ft) long.[2] There will be 17 sharp curves along the route; the sharpest curve will have a radius of 120 metres (390 ft).[142]

# Station name[143] Chainage (km) Distance from previous station (km) Platform type Alignment description[144]
English Malayalam
1 Aluva ആലുവ -0.090 0 Side On 1000 metres curve
2 Pulinchodu പുളിഞ്ചോട് 1.814 1.904 Side Curved
3 Companypady കമ്പനിപ്പടി 2.756 0.942 Side Straight
4 Ambattukavu അമ്പാട്ടുകാവ് 3.764 1.008 Side Straight
5 Muttom മുട്ടം 4.723 0.959 Side & Island Straight Curved
6 Kalamassery കളമശ്ശേരി 8.144 Side Straight
7 Cochin University കൊച്ചിൻ യൂണിവേഴ്‌സിറ്റി Unknown Side Straight
8 Pathadipalam പത്തടിപ്പാലം 9.146 Side Straight
9 Edappally ഇടപ്പള്ളി 12.023 Side Straight
10 Changampuzha Park ചങ്ങമ്പുഴ പാർക്ക് Unknown Side Straight
11 Palarivatom പാലാരിവട്ടം 13.071 Side Straight
12 JLN Stadium ജെ. എൽ. എൻ സ്റ്റേഡിയം 14.126 1.055 Side Straight
13 Kaloor കലൂർ 15.221 1.095 Side Straight
14 Lissie ലിസ്സി 15.711 0.490 Side Straight
15 M.G. Road എം. ജി റോഡ്‌ Unknown Side Straight
16 Maharaja's College മഹാരാജാസ് കോളേജ് 16.899 Side Straight
17 Ernakulam South എറണാകുളം സൗത്ത് 19.332 1.229 Side Straight
18 Kadavanthra കടവന്ത്ര Unknown Side Straight
19 Elamkulam എളംകുളം 21.341 Side Straight
20 Vyttila വൈറ്റില 22.447 1.106 Side Straight
21 Thaikoodam തൈക്കൂടം 23.703 1.256 Side Straight
22 Petta പേട്ട 24.822 1.119 Side Straight
23 Alliance Junction അലയൻസ് ജംഗ്ഷൻ Side Straight
24 SN Junction എസ്.എൻ ജംഗ്ഷൻ Side Straight
25 Tripunithura തൃപ്പൂണിത്തുറ Side Straight

Infrastructure

Rolling stock

The Kochi Metro uses 65 metre long Metropolis train sets built and designed by Alstom.[145] Coaches are be 3.90 metres (12.8 ft) tall, and each train of three coaches will be 65 metres (213 ft) in length.[146] Each coach will have three wide doors, with automatic door closing and opening.[147] The platforms at each station will be 70 metres (230 ft) long,[146] and will have half platform screen doors.[147] A total of 22 trains will be inducted for the first phase of operations of the metro.[148] The axle load is 15 t (15 long tons; 17 short tons) for which the structures are to be designed. The capacity of each train is 975 passengers.[147]

It was initially proposed to use maglev trains from South Korea for Kochi Metro.[149] It was later decided that Kochi Metro will run on standard gauge, with 3 coaches initially in each train, which can be extended to six coaches in future.[150] The width of each coach was fixed at 2.70 metres (8 ft 10 in) in the DMRC's original DPR. However, KMRL wanted the metro to be as a medium metro corridor, as opposed to a light one, and the width was increased to 2.90 metres (9 ft 6 in).[151]

The DMRC floated a global tender in July 2013 for the manufacture and design of the coaches. Hyundai-Rotem/BMEL-India and Band Changchun Railway Vehicle Co Ltd[152] were the only bidders, when the bids were opened in December 2013. The Chinese firm did not qualify, leaving only the Hyundai consortium in contention.[153] The 7.50 billion contract was re-tendered on 10 March 2014,[154] and the coach width requirement was changed.[147] The DMRC opposed re-tendering, stating that it might delay the metro's opening, by up to a year or more. It also argued that coaches supplied by Hyundai Rotem were already in use on the Delhi Metro, as well as a few other metros.[155] According to metro officials, "The delay will impact integrated trial of coaches in Aluva-Palarivattom route, initially scheduled from August 2015. With retendering process on, the proposed integration of coaches with tracks, third traction (sourcing power from third rail) and signal systems can be done only by 2015-end or early 2016."[153]

The DMRC held a pre-bid meeting in New Delhi on 2 April 2014 to allow interested firms to seek clarifications regarding technical specifications for the contract for the coaches.[152]

Power

KMRL will acquire 20MW of electricity annually, to operate the metro. The electricity will by supplied from the Kaloor substation of the Kerala State Electricity Board (KSEB).[156] The DMRC was in favour of supplying power through 25 KV overhead power lines. This was opposed by the KMRL who preferred to source power from the third rail laid alongside metro track. It was decided to supply power via the 750 V DC third rail.[157]

Parking

KMRL assigned Cochin University of Science and Technology (CUSAT) to conduct a feasibility study on incorporating parking spaces on the metro rail corridor. The study was focused in understanding the ridership of all 22 stations including two terminal stations and assessing the possible number of two and four wheelers, which would require parking in the Aluva- Pettah Metro Rail corridor. As part of the study the School of Management Studies (SMS) also prepared the layout for parking with traffic circulation plan for each station. The SMS submitted the report on 10 August 2012.[158] preliminary report was submitted in June 2012. CUSAT was given the task, as the report submitted by DMRC did not have specifications regarding the parking facilities.[159] The DMRC's DPR mentioned parking lots only at the 2 terminal stations - Aluva and Pettah.[160] CUSAT's detailed study was submitted on 10 August 2012. The study proposed parking lots adjacent to all stations with some having multi-level parking. In some stations, parking facilities connected to the station via walkways will be located away from the station due to lack of available land.[161] KMRL will consider introducing shuttle services between parking lots and stations if the distance is long. SMS will work out the requirement of land that has to be acquired for this. KMRL says parking facilities will prevent traffic congestion and integrate personal transport system with mass rapid transit systems.[162]

Stations

Design

The interiors of the Kochi Metro stations will be decorated with references to local culture. However, the traditional nālukettu architectural style was not structurally feasible.[163] According to a KMRL official, "It [stations] will be designed in such a way that it reflects the Kerala style of architecture with each of the 22 stations reflecting a regional theme. ... the stations will reflect an independent adaptation of the state's culture to give it a distinct look".[164] KMRL officials stated, "Our effort is to highlight the uniqueness of the state, especially to outsiders, but the station buildings won't be an exact replica of the Kerala model of architecture. The station designs are contemporary, but inspired by socio-cultural themes. The kettuvalam or houseboat, for example, widely used in the backwaters of the state, will be the theme of one of the stations, bearing descriptions of how it is made with a model exhibited alongside."[165]

Egis India is responsible for the design of the stations such as floors and doors, and the Indian Institute of Architecture (Kochi Chapter) developed the designs of roof and the interior of the stations.[166] The IIA presented the designs of 14 stations to the KMRL on 14–15 March 2014.[167]

Operations

Name

It was initially reported in the Indian media that the Kochi Metro would be officially named Komet (a short form of the name Kochi Metro). The name was reportedly accepted by KMRL's first MD, Tom Jose, and the logo was designed based on that name. However, it was alleged that Jose had made the decision unilaterally without reaching a consensus.[168] On 22 June 2013, The New Indian Express reported that Livespace, a company hired to produce an animated demo video for the metro, had been told by KMRL officials to remove the name Komet that was used in the video and instead use the name Kochi Metro.[169] However, The Hindu reported the next day that a formal decision had not been taken regarding the name.[168]

Boat service

A boat service from Vyttila to Kakkanad, operated by the Kerala State Water Transport Department (KSWTD) was launched on 19 November 2013.[170] It is integrated with the metro, and was used for diverting traffic during construction of the metro. The boats were manufactured at Steel Industries Kerala Ltd, Kannur (part of Steel Authority of India Ltd). The boats complete the 9 km[171] Vyttila-Kakkanad journey in approximately 25 minutes.[172]

Criticism

Some have criticised Kochi Metro as another loss making public transport project. As the Kerala and Union Governments have given only Rs. 1,500 crore, KMRC will have to borrow Rs. 3,600 crore from various banks with 1.5% interest on 20 years repayment.[173] The estimated daily ridership in Kochi Metro is 50,000 and estimated annual Income is 27 crore. Loan interest, repayment and operation cost will cost Kochi Metro Rs. 252 Crore annually. Some studies suggest that Kochi Metro will make a loss of Rs 245 crore per year. Then, as per the rules, the Kerala Government will have to pay this amount to investors every year.[173]

Project updates

References

  1. "Contact Us". Kochimetro.org. Retrieved 10 March 2012.
  2. 1 2 3 4 5 "Kochi Metro trains to have 3 coaches to carry 1,000 passengers". NDTV. Press Trust of India. 24 May 2013.
  3. http://web.archive.org/web/20120715014717/http://www.ianslive.in:80/news/Metro_reaches_Kochi-387644/LatestNews/31. Archived from the original on 15 July 2012. Retrieved 4 July 2012. Missing or empty |title= (help)
  4. "DMRC issues tender for Kochi metro trains |". International Railway Journal. 23 July 2013. Retrieved 28 September 2013.
  5. "Metro rail: DMRC demands prompthanding over of land, funds". The Hindu (Chennai, India). 24 March 2012. Retrieved 24 March 2012.
  6. "DMRC sets early deadline for Kochi Metro rail project". The Times of India. 26 May 2013. Retrieved 27 June 2013.
  7. "Heading for a dead-end". The New Indian Express. 6 July 2010. Retrieved 7 January 2012.
  8. "Metro dreams get a start". Deccan Chronicle. 8 June 2013. Retrieved 27 June 2013.
  9. "Six years on, Kochi Metro to see faster progress now". Business Standard. 25 October 2011. Retrieved 7 February 2014.
  10. "Nod for Metro project's revised proposal". The Times of India. 16 October 2011.
  11. "Kochi Metro Rail gets Public Investment Board's approval". The Economic Times. 1 January 1970. Retrieved 23 March 2012.
  12. "Kochi Metro gets nod from public Investment: Board". News.webindia123.com. Retrieved 23 March 2012.
  13. "DMRC to carry out Kochi Metro work". CNN IBN. 29 March 2012. Retrieved 27 June 2013.
  14. "It's official: DMRC to drive Kochi Metro". The Times of India. 29 March 2012.
  15. "Centre nod for Kochi Metro". Times of India. 4 July 2012.
  16. "Tom Jose shunted out of Kochi Metro". CNN IBN. 17 August 2012. Retrieved 27 June 2013.
  17. "Kochi Metro project could have been implemented without DMRC". Business Standard. 16 August 2012. Retrieved 27 June 2013.
  18. "Board of Kochi Metro Rail Ltd reconstituted". Business Standard. 14 August 2012. Retrieved 27 June 2013.
  19. "AFD team to visit Kochi". The Hindu. 12 April 2013. Retrieved 27 June 2013.
  20. "Kochi Metro: French funding to materialise by December". The New Indian Express. 27 April 2013. Retrieved 27 June 2013.
  21. "‘Win-win pact’ for Kochi metro". The Hindu. 5 April 2013. Retrieved 27 June 2013.
  22. Special Correspondent (20 June 2013). "Cabinet nod for 22 metro stations in Kochi". The Hindu. Retrieved 27 June 2013.
  23. Nangia, Tarun (24 May 2013). "Kochi Metro Rail crosses a milestone". The New Indian Express. Retrieved 27 June 2013.
  24. Sanandakumar, S (28 October 2012). "Kochi Metro, other ambitious Kerala projects not a cake walk for E Sreedharan". Economic Times (Times Internet). Retrieved 6 September 2014.
  25. "Metro Man to have last word". CNN IBN. 10 May 2011. Retrieved 7 January 2012.
  26. "DMRC to build, Sreedharan to guide Kochi Metro". Daily Pioneer. 10 July 2012.
  27. Special Correspondent (16 October 2012). "State firm on DMRC implementing Kochi metro". The Hindu. Retrieved 27 June 2013.
  28. "English News | Kerala". Manorama Online. 23 May 2013. Retrieved 27 June 2013.
  29. Updated Thursday, 27 June 2013 12:00 PM IST (23 May 2013). "English News | Kerala". Manorama Online. Retrieved 27 June 2013.
  30. "Support DMRC for Kochi Metro | A campaign launched by the Mayor of Cochin Sri. Tony Chammany". Archived from the original on 8 March 2013.
  31. "Kochi Mayor launches Facebook campaign for DMRC". The Hindu. 26 October 2012. Retrieved 27 June 2013.
  32. PTI (1 December 2012). "Kochi Metro asked to get DMRC support". The Hindu Business Line. Retrieved 27 June 2013.
  33. PTI (1 December 2012). "JICA asks Kochi Metro to use expertise of DMRC". Economic Times. Retrieved 27 June 2013.
  34. "Kochiites join hands for their dream Metro". The Times of India. 29 October 2012. Retrieved 27 June 2013.
  35. "Keralites to form 25km ‘human metro’ in protest". Khaleej Times. 24 October 2012. Retrieved 27 June 2013.
  36. 1 2 "North bridge, a concrete testimony to efficiency". The Hindu. 29 December 2013. Retrieved 7 February 2014.
  37. "Rs 48.88 crore earmarked for metro land acquisition". The New Indian Express. 11 March 2013. Retrieved 27 June 2013.
  38. "Land acquisition major issue". Deccan Chronicle. 9 January 2013. Retrieved 27 June 2013.
  39. "Delhi focus only on Kochi Metro". Deccan Chronicle. 27 January 2013. Retrieved 27 June 2013.
  40. Winds of change over Kochi - southindia - Kochi - ibnlive
  41. "Cities / Kochi : Rs.15 crore handed over to DMRC". The Hindu (Chennai, India). 4 March 2012. Retrieved 10 March 2012.
  42. "Kochi Metro Rail hands over rs 15 crore to DMRC". The Economic Times. 3 March 2012. Retrieved 10 March 2012.
  43. "Kochi Metro Rail hands over rs 15 crore to DMRC, IBN Live News". CNN IBN. 3 March 2012. Retrieved 10 March 2012.
  44. Kochi Bureau (20 March 2012). "Cities / Kochi : Kochi metro on fast track". The Hindu (Chennai, India). Retrieved 23 March 2012.
  45. Special Correspondent (30 May 2013). "10,000 encroachers to get title deeds". The Hindu. Retrieved 27 June 2013.
  46. 1 2 "Infrastructure Makes Inroads". The New Indian Express. 31 December 2013. Retrieved 7 February 2014.
  47. 1 2 M. P. Praveen (31 December 2013). "The ebb and flow of fortune in a coastal city". The Hindu. Retrieved 7 February 2014.
  48. "Growing by Leaps and Bounds". The New Indian Express. 31 December 2013. Retrieved 7 February 2014.
  49. "RoB as part of Kochi metro completed". Business Standard. 12 May 2013. Retrieved 27 June 2013.
  50. "Overbridge to be named after A.L. Jacob, says CM". The Hindu. 13 May 2013. Retrieved 27 June 2013.
  51. "Over to Edappally Junction flyover". The Times of India. 13 May 2013. Retrieved 27 June 2013.
  52. "AL Jacob flyover opens". Deccan Chronicle. 13 May 2013. Retrieved 27 June 2013.
  53. 1 2 "Kochi Metro work to begin on June 7". The Times of India. 13 May 2013. Retrieved 27 June 2013.
  54. "DMRC fine-tuning traffic regulation blueprint". The New Indian Express. 10 May 2013. Retrieved 27 June 2013.
  55. 1 2 Alexander, Princy. "Banerjee Road widening in full swing". The New Indian Express. Retrieved 27 June 2013.
  56. "Petta-Vyttila road halts Metro work". Deccan Chronicle. 11 April 2008. Retrieved 7 February 2014.
  57. "4th reach to start soon". Deccan Chronicle. 12 November 2013. Retrieved 7 February 2014.
  58. "National / Kerala : KMRL completes resurfacing of roads". The Hindu (Chennai, India). 25 February 2012.
  59. "Agreement for Rs 108-crore flyover at Edappally inked". Deccan Chronicle. 23 July 2013. Retrieved 28 September 2013.
  60. "Edapally flyover work on hold". Deccan Chronicle. 12 January 2014. Retrieved 7 February 2014.
  61. http://www.thehindu.com/news/cities/Kochi/kerala-hc-criticises-kochi-corporation-over-pachalam-overbridge/article5716428.ece
  62. 1 2 http://timesofindia.indiatimes.com/city/kochi/Corporation-gives-in-principle-approval-for-Pachalam-ROB/articleshow/30208320.cms
  63. http://timesofindia.indiatimes.com/city/kochi/Govt-OKs-Pachalam-ROB/articleshow/31061848.cms
  64. http://www.thehindu.com/news/cities/Kochi/kochi-corporation-okays-pachalam-rob/article5676421.ece
  65. http://www.newindianexpress.com/cities/kochi/Stone-Laid-for-Pachalam-Railway-Overbridge/2014/03/05/article2090526.ece#.Uxg96UDDDIU
  66. http://www.thehindu.com/news/cities/Kochi/pachalam-overbridge-to-be-up-in-six-months/article5745872.ece
  67. http://www.thehindu.com/todays-paper/tp-national/tp-kerala/city-needs-decentralised-hubs-says-transportation-expert/article2894922.ece
  68. "Metro station at Vyttila mobility hub on the cards". The Hindu (Chennai, India). 29 February 2012.
  69. "KMRL to build inspection ramp for KSRTC". Deccan Chronicle (Chennai, India). 25 November 2011.
  70. "KSRTC to use Ambedkar stadium for parking purpose". The Times of India (Chennai, India). 25 June 2012.
  71. "Thevara-Perandoor Canal Dredging Kicks Off". Chennai, India: Dredging Today. 11 April 2012.
  72. "Kochi Metro ‘needs more land than projected’". The Hindu Business Line. Retrieved 27 June 2013.
  73. "Kochi metro will require 40.4 hectare land". Business Standard. 19 November 2012. Retrieved 27 June 2013.
  74. "Kochi metro requires eight more hectares". The Hindu. 16 November 2012. Retrieved 27 June 2013.
  75. "KMRL reveals final alignment of Kochi Metro". The Times of India. TNN. 16 November 2012. Retrieved 27 June 2013.
  76. "Revenue survey will have final say on metro land". The Hindu. 16 November 2012. Retrieved 27 June 2013.
  77. John L. Paul (17 October 2012). "Kochi Metro Rail: No clarity on how much land is needed". The Hindu. Retrieved 27 June 2013.
  78. "Panel approves land value fixed for Metro". The Times of India. TNN. 16 October 2012. Retrieved 27 June 2013.
  79. "Rates finalised for Kochi land acquisition". The Hindu. 16 October 2012. Retrieved 27 June 2013.
  80. 1 2
  81. 1 2 "Kochi Metro land cost revised to 1,110 crore". The Times of India. TNN. 29 November 2012. Retrieved 27 June 2013.
  82. http://www.thehindu.com/news/cities/Kochi/land-for-kochi-metro-station-handed-over/article5688464.ece
  83. http://www.newindianexpress.com/cities/kochi/GCDA-Hands-Over-30-Cents-for-Kochi-Metro/2014/02/14/article2055755.ece#.UxhnLkDDDIU
  84. http://www.thehindu.com/news/cities/Kochi/kochi-metro-operations-control-centre-to-be-established-at-muttom/article5772973.ece
  85. http://www.newindianexpress.com/cities/kochi/Land-Acquisition-to-be-Smoothened/2014/03/08/article2097384.ece#.UyAQdUDDDIU
  86. http://timesofindia.indiatimes.com/city/kochi/Land-for-Metro-will-be-ready-in-3-months/articleshow/31631219.cms
  87. "The Pioneer". Dailypioneer.com. 1 January 1970. Retrieved 27 June 2013.
  88. V. Sajeev Kumar (13 September 2012). "More cities may come under Metro rail ambit". The Hindu Business Line. Retrieved 27 June 2013.
  89. "PM inaugurates Kochi Metro project". Zeenews. 13 September 2012. Retrieved 27 June 2013.
  90. "Metro Rail work to kickstart in style". The New Indian Express. 21 May 2013. Retrieved 27 June 2013.
  91. "Kochi Metro work to begin on Friday". The Times of India. TNN. 4 June 2013. Retrieved 27 June 2013.
  92. "Indian state begins work on metro rail". gulftoday.ae. 8 June 2013. Retrieved 27 June 2013.
  93. "Your Metro ride 1,094 days away". The Times of India. TNN. 8 June 2013. Retrieved 27 June 2013.
  94. "Green signal awaited for metro extensions". The Hindu. 8 June 2013. Retrieved 27 June 2013.
  95. "Piling for 1st Metro station begins". The New Indian Express. 1 October 2013. Retrieved 7 February 2014.
  96. "Work on metro’s first station to begin at Kaloor from Monday". The Hindu. 23 September 2013. Retrieved 28 September 2013.
  97. Alexander, Princy (23 September 2013). "Piling work for first metro station set to begin". The New Indian Express. Retrieved 28 September 2013.
  98. "No casting yard for DMRC, metro works may derail". Deccan Chronicle. 17 June 2013. Retrieved 27 June 2013.
  99. "Metro work: Steps in place to curb traffic". The New Indian Express. 1 June 2013. Retrieved 27 June 2013.
  100. "Traffic regulation plan for metro works in final stage". The Hindu. 21 June 2013. Retrieved 27 June 2013.
  101. "Agreement to be signed soon: KMRL". The Hindu. 5 May 2013. Retrieved 27 June 2013.
  102. "Alternative routes planned to divert traffic during Kochi metro rail work". The Hindu. 17 May 2013. Retrieved 27 June 2013.
  103. News, Express (6 June 2013). "Metro work to get under way Friday". The New Indian Express. Retrieved 27 June 2013.
  104. "Imported sand could be used for Metro construction". The Times of India. 23 October 2013. Retrieved 7 February 2014.
  105. Priyadershini S. (6 June 2013). "New trees for old ones". The Hindu. Retrieved 27 June 2013.
  106. "Metro rail project: Trees axed for widening of road". The New Indian Express. 17 June 2013. Retrieved 27 June 2013.
  107. "DMRC begins compensatory tree-planting mission". The New Indian Express. 22 June 2013. Retrieved 27 June 2013.
  108. "KMRL Vows to Give City a Green Cover". The New Indian Express. 16 December 2013. Retrieved 7 February 2014.
  109. "Metro train set to land in 20 months: Sreedharan". Deccan Chronicle. 17 July 2013. Retrieved 28 September 2013.
  110. "Metro coaches to arrive by May 2015 - Times Of India". Articles.timesofindia.indiatimes.com. 17 July 2013. Retrieved 28 September 2013.
  111. "Sreedharan wants to finish Metro ahead of deadline". Deccan Chronicle. 14 July 2013. Retrieved 28 September 2013.
  112. 1 2 John L. Paul (15 December 2013). "500 piles completed in Metro Rail's Aluva-international stadium reach". The Hindu. Retrieved 7 February 2014.
  113. "Era Constructions may be Replaced for Shoddy Work". The New Indian Express. 15 December 2013. Retrieved 7 February 2014.
  114. "Metro Work: Contractor Replaced". The New Indian Express. 30 December 2013. Retrieved 7 February 2014.
  115. 1 2 "Soma replaces Era for Metro construction". Deccan Chronicle. 14 January 2014. Retrieved 7 February 2014.
  116. John L. Paul (12 January 2014). "New contractors to take up Kochi metro civil works". The Hindu. Retrieved 7 February 2014.
  117. "DMRC begins preliminary works on SA Road stretch". The Times of India. TNN. 17 January 2014. Retrieved 7 February 2014.
  118. "Protests derail Metro: 45 work days, Rs 18 crore lost in process". The Times of India. TNN. 29 January 2014. Retrieved 7 February 2014.
  119. http://www.thehindu.com/news/cities/Kochi/kmrl-vows-to-clear-hurdles-in-metro-work/article5728551.ece
  120. "We told you so: Deadline for Metro". Times Internet. 5 March 2014. Retrieved 26 October 2014.
  121. http://www.newindianexpress.com/cities/kochi/First-U-shaped-Concrete-Girder-of-Metro-Rail-Project-Installed-in-Aluva/2014/07/13/article2328103.ece
  122. http://www.railwaygazette.com/news/urban/single-view/view/kochi-metro-begins-test-running.html
  123. "Final word on Kochi Metro’s terminal station by January". The Hindu. 23 October 2013. Retrieved 7 February 2014.
  124. "Kochi metro up to Tripunithura". The Hindu. 28 January 2014. Retrieved 7 February 2014.
  125. "Metro: Tripunithura in Phase I". The New Indian Express. 28 January 2014. Retrieved 7 February 2014.
  126. http://www.thehindu.com/news/cities/Kochi/cabinet-nod-for-extension-of-kochi-metro-project/article5756152.ece
  127. "Union Cabinet nod for Rs 5,146 crore Kochi Metro expected soon: Official". The Times of India. 21 December 2011.
  128. "RITES to study feasibility". Deccan Chronicle. 6 July 2013. Retrieved 28 September 2013.
  129. Our Bureau (5 July 2013). "Feasibility study for Kochi Metro expansion okayed | Business Line". Thehindubusinessline.com. Retrieved 28 September 2013.
  130. "Kochi metro rail project approved". Newstrackindia.com. 4 July 2012. Retrieved 27 June 2013.
  131. 1 2 "Will ask Centre for more funds for Kochi Metro". The Times of India. 1 May 2012.
  132. "Metro hunts for more funding options". The Hindu. 5 December 2012. Retrieved 27 June 2013.
  133. 1 2 "Government Jacks up Aid for Kochi Metro". The New Indian Express. 5 December 2013. Retrieved 7 February 2014.
  134. "Credit line opened for Kochi Metro". The Hindu. 5 November 2013. Retrieved 7 February 2014.
  135. "Kochi metro now links Thripunithura in Phase I". Business Standard. 28 January 2014. Retrieved 7 February 2014.
  136. http://www.thehindu.com/news/cities/Kochi/kmrl-to-sign-rs-1500crore-loan-agreement-with-french-agency/article5626034.ece
  137. http://www.thehindu.com/news/cities/Kochi/kmrl-scouts-for-revenue-sources-for-metro/article5589759.ece
  138. http://articles.economictimes.indiatimes.com/2014-07-16/news/51600810_1_kochi-metro-rail-ltd-loan-agreement-elias-george
  139. http://www.thehindubusinessline.com/news/states/canara-bank-signs-1170cr-loan-pact-for-kochi-metro/article6230919.ece
  140. "Metro Stations". Kochimetro.org. Retrieved 27 June 2013.
  141. "For starters, you can catch a Metro every 5 minutes". The Times of India. TNN. 25 May 2013. Retrieved 27 June 2013.
  142. http://kochimetro.org/wp-content/uploads/2013/07/stattions.pdf
  143. Delhi Metro Rail Corporation (August 2011). "Detailed Project Report : Kochi Metro Project Alwaye - Petta Corridor" (PDF). Kochi Metro. Retrieved 16 November 2013. This article incorporates text from this source, which is in the public domain.
  144. http://economictimes.indiatimes.com/slideshows/infrastructure/alstoms-new-metropolis-train-set-for-kochi-metro/slideshow/48952471.cms
  145. 1 2 "Metro train to ply every 5 minutes, carry 1,000 persons". The Hindu. 25 May 2013. Retrieved 27 June 2013.
  146. 1 2 3 4 http://www.thehindu.com/news/cities/Kochi/low-number-of-bidders-not-to-affect-quality-and-safety-of-kochi-metro/article5418814.ece
  147. "Metro rail: 22 trains in the first phase". The New Indian Express. 25 May 2013. Retrieved 27 June 2013.
  148. "Magnetic levitation technology for Kochi metro rail mooted". The Hindu (Chennai, India). 17 November 2011.
  149. "No Maglev tech for Kochi Metro". The Times of India. 15 February 2012. Retrieved 10 March 2012.
  150. http://articles.timesofindia.indiatimes.com/2013-10-12/kochi/42967447_1_kochi-metro-rail-ltd-kmrl-rapid-metro
  151. 1 2 http://www.thehindu.com/news/cities/Kochi/prebid-meeting-for-kochi-metro-coaches-held/article5865927.ece
  152. 1 2 http://www.thehindu.com/news/cities/Kochi/coach-retender-unlikely-to-affect-allied-metro-works-in-kochi/article5795420.ece
  153. http://www.thehindu.com/news/cities/Kochi/dmrc-to-meet-prospective-coach-suppliers-for-kochi-metro-today/article5861645.ece
  154. http://www.thehindu.com/news/cities/Kochi/dmrc-to-meet-prospective-coach-suppliers-for-kochi-metro-today/article5861645.ece
  155. Greeshma Gopal Giri (18 September 2012). "KMRL to seek 20MW from KSEB for metro". The Times of India. Retrieved 27 June 2013.
  156. http://www.thehindu.com/news/cities/Kochi/dmrc-to-meet-prospective-coach-suppliers-for-kochi-metro-today/article5861645.ece
  157. "Cities / Report on metro parking submitted". The Hindu (Kochi, India). 11 August 2012.
  158. "Cities / Kochi : Parking in metro stations: Cusat school to do feasibility study". The Hindu (Chennai, India). 11 March 2012. Retrieved 23 March 2012.
  159. "Cities / Kochi : Kochi metro stations may get multi-tier parking lots". The Hindu. 13 November 2012. Retrieved 14 November 2012.
  160. "Report on metro parking submitted". The Hindu. 11 August 2012. Retrieved 27 June 2013.
  161. "Cusat to help prepare report for Kochi Metro". The Times of India. 1 January 1970. Retrieved 10 March 2012.
  162. http://newindianexpress.com/cities/kochi/Slice-of-local-culture-in-metro-stations/2013/07/20/article1692846.ece
  163. http://www.deccanchronicle.com/130812/news-current-affairs/article/meeting-finalize-design-kochi-metro-rail-stations
  164. http://web.archive.org/web/20140102200318/http://www.asianage.com/india/metro-stations-wear-heritage-495
  165. http://timesofindia.indiatimes.com/city/kochi/14-station-designs-submitted-to-Kochi-Metro-Delhi-Metro-for-approval/articleshow/32225948.cms
  166. http://timesofindia.indiatimes.com/city/kochi/14-station-designs-submitted-to-Kochi-Metro-Delhi-Metro-for-approval/articleshow/32225948.cms
  167. 1 2 "It is ‘Kochi Metro’". The Hindu. 22 June 2013. Retrieved 27 June 2013.
  168. Shibu B S (22 June 2013). "'Kochi Metro' rises as 'Komet' crashes". The New Indian Express. Retrieved 27 June 2013.
  169. http://newindianexpress.com/cities/kochi/Vyttila-Kakkanad-boat-service-to-set-sail-on-November-19/2013/11/05/article1872337.ece
  170. http://newindianexpress.com/cities/kochi/Boat-service-from-Vyttila-next-month/2013/08/05/article1718229.ece
  171. http://www.deccanchronicle.com/130805/news-current-affairs/article/first-metro-feeder-september
  172. 1 2 http://www.scorpiogenius.com/2009/08/cochin-metro-essential-or-extravagence.html
  173. "Finally, a Kochi dream gets wheels", The Hindu, 24 Jan 2016, http://www.thehindu.com/news/cities/Kochi/finally-a-kochi-dream-gets-wheels/article8147013.ece?ref=tpnews
  174. "Kochi Metro to start operations on Kerala Formation Day: Chandy", The Hindu, 24 Jan 2016, http://www.thehindu.com/news/cities/Kochi/kochi-metro-to-start-operations-on-kerala-formation-day-chandy/article8145912.ece

External links

Wikimedia Commons has media related to Kochi Metro.


Geographic data related to Kochi Metro at OpenStreetMap

This article is issued from Wikipedia - version of the Tuesday, May 03, 2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.