Shenyang Modern Tram

For the first generation tram system in Shenyang, see Trams in Shenyang.
Shenyang Tramway Network

Shenyang New Tram in front of airport
Operation
Locale Shenyang, People's Republic of China China
Open 15 August 2013
Lines 3
Infrastructure
Track gauge 1,435 mm (4 ft 8 12 in) standard gauge
Horse Tram era
Track gauge 1,435 mm (4 ft 8 12 in) standard gauge
Japanese-Owned era: 1925–1973
Track gauge 1,435 mm (4 ft 8 12 in) standard gauge
Current era: 2013
Track gauge 1,435 mm (4 ft 8 12 in) standard gauge
Track length (double) 70 km [1]
Stops 65

Shenyang Modern Tram is the first partly battery powered tram both in China and Asia. This tram system mostly uses traditional overhead wire system, but partly uses charged battery system, without overhead wire.

Shenyang once had a standard steel wheeled tramway net work.. It first was opened as horse tram and later converted to electric tram. Routes were built step by step, and it reached their most widespread network in 1945 with 170 tramcars. But like most cities around the world during the sixties & seventies, the tram service was completely stopped in 1974.

Tram returned in Shenyang in 2012. Commercial service started in 2013. Shenyang Modern Tram started construction in June 2012. In August 15, 2013, Shenyang tram trial operation started, and in 15 September 2013 officially passenger operations started. The whole plan of Shenyang Modern Tram is running from Olympic Centre, near Aoizhongxin station of Shenyang Metro Line 2 to Shenfu Xincheng, Expo Centre and Taoxian Airport. Now the 54.8-km-long 1st phase. include two stops which can change to Shenyang Metro Line 2, one is Aoizhongxin, the other is Baitahelu, operating mileage of China's longest tram system. Shenyang tram use BT model investment by the CNR 4.82 billion yuan by the construction and Veolia Transport Paris Metro Chinese company transportation management (Veolia Transport is now by the French Transport Development Group substituted).

History

After closing tram network in seventies, people of Shenyang thought the only un fashioned obstacle of smooth city traveling has removed, and the city can move faster than before, but it proved false some years later. Uncontrolled increasing of petrol vehicles like bus, taxicab, and private car started chocking the streets of Shenyang. Like most Asian countries, China suffered by many problems of developing countries, including pollution, traffic jam, illegal migration, low literacy and booming increasing of population etc. Increasing population started increasing urbanization of Shenyang, and it started increasing motor vehicles, which started increasing air & sound pollution, traffic jam & smog. The city even became slower than pre-tram closure era. From starting '80, all this problems started and at mid '90, inhabitants of Shenyang realized that non-controlling of motor vehicles & closure of tram was a great mistake. Many cities around the world like Tunis, Algiers, Oran, Sydney, Buenos Aires, Pyongyang, Dublin, Edinburgh, Athens, Bergen etc. also understood that error, and like them, two Chinese cities Tianjin & Shanghai also returned tram. Mainly looking Tianjin & Shanghai, Shenyang also planned for return of tram.

Understanding the great mistake of former tram closure, government started to decrease pollution as soon as possible. Looking many cities around the world i.e. - Algiers, Buenos Aires, Athens, Pyongyang, Tianjin, Shanghai etc., authority planned to return trams in Shenyang. But then number of cars & buses had already increased very much in Downtown Shenyang, so opening a tramway system were not possible there. Minding this, transport authority decided to construct it in the south of Hun He, which is in southern side of the main city. Shenyang's transport authority at last decided to open a separate, modern, high speed partly battery powered tram.

December 1, 2011, Shenyang City, announced plans to open five lines in March 2012 to build "Hunnan modern streetcar project" plan, a total length of 65 km, in April 2013 trial run, June 2013 officially put into use . February 17, 2012, the project started construction, according to the revised timetable on the progress of the project groundbreaking ceremony, Shenyang new tram system will be test run in March 2013, the formal operation in June, a construction line Save of four, full-length was reduced to about 60 kilometres. tramways actual passenger test run on August 15, September 15 official ticketing operation. The line is operated by Shenyang Hunnan Modern Transportation Operations Limited.

The new system was chosen for south Shenyang, because it is a less congested and planned area, and commuting between one place to another in that area has become a serious problem. It was selected as a partly battery operated system, because it will reduce use of overhead-wire, which makes an eyesore for some people. Another advantage of this type of tram is they will utilize much less electricity for using recharged battery, so it will reduce production of electricity lesser in power station, so it is more eco-friendly

Past in a nutshell

Tram routes

Practical Info

Fleet

The 30 low-floor trams are manufactured by Voith, together with the Chinese manufacturer Changchun Railway Vehicles Company. All trams are low floor, fully air conditioned, can run high speed. Each tram has three cars. It takes electricity via pantograph.

Features

The entire Shenyang Modern tram network is hybrid type. It partly runs on unreserved grooved-rail track by sharing with other vehicles, partly runs on unreserved segregated track with raised rail with granite stones like mainline railway which is completely separated from other vehicles. In some parts it runs on reserved grassy track also. Some area has overhead wire free, especially near Airport due to safety of airplane flying and in some city area also. At those area, tramcars stop at a stoppage for 30 seconds, and at at time rise their pantographs towards overhead charging-special catenary. After charging the battery by this, they start moving again towards the next stop, where they would recharge again.

Depots & termini

The only tram depot is at Hunnan. Termini are Olympic Centre, Shenfu Xincheng, Expo Centre and Taoxian Airport.

Alignment and Interchanges

The modern tram routes partly run on unreserved track at middle of the road, partly on grass-bed, partly on raised rail track.

Interchanges become with Shenyang Metro Line 2 - one is at Aoizhongxin, the other is at Baitahelu.

Tickets

The implementation of a single one-way fare 2 Yuan. Tram payment tentative two kinds, namely coin and card; non-segmented accounting.

Projects

Route 3 is under construction. It will run from Century Buliding, (where interchange will be possible with metro line 2 station Shijidasha) - to Expo Centre via University Science City. At North-eastern Univercitry it will meet with route 1. This new route is expected to open in 2016.

Criticism

The modern tram of Shenyang is very popular & useful for daily passengers & inhabitants of South Shanyan. It's great looking impresses very much about citizens. Although some criticize that it is a bit expensive due to partly wire-free section. It is a great example that a modern tram network is completely alternation of a metro network where population density is lower, roads are wider.

Accidents

See also

Trams in Shenyang - the first generation tramway network

Shenyang Metro

Shenyang suburban train

Anren Tram

Changchun Tram

Dalian Tram

Hongkong Tram

Qingdao Tram

Suzhou Tram

Tianjin Modern Tram - rubber tired tram of Tianjin

Shanghai Modern Tram - rubber tired tram of Shanghai

References

  1. "Shenyang Tramway". Railway-Technology. Retrieved 30 January 2015.

External links

This article is issued from Wikipedia - version of the Friday, May 06, 2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.